Data Center Testing and Commissioning Checklist
Planning, FAT, site receipt, pre-commissioning, functional tests, load-bank tests, integrated failure scenarios, defect closure, and acceptance evidence for data center commissioning.
How to use this tracker
Each row is an executable work package. Assign a named individual against the accountable role, enter planned start and end dates, follow the predecessor task IDs, and mark a task complete only when its completion criterion is met and supporting evidence has been reviewed.
The owner column deliberately contains the accountable role, not a person’s name, so the tracker stays reusable across organisations. Add a Named_Ownercolumn — or use the local “Named owner” field on each task below — in your working copy.
Using it in Excel
- Import the file as UTF-8.
- Convert the imported range into an Excel Table.
- Freeze the header row.
- Use ISO dates in YYYY-MM-DD format.
- Add data-validation lists for Status and Applicability.
- Filter Critical tasks and blocked project gates during every project review.
- Add a Named_Owner column in the working copy.
- Record the accepting authority in Notes for Accepted Risk.
- Preserve stable Task IDs when customising the tracker.
- Do not mark a task complete until its evidence has been reviewed.
Status legend
- Not Started
- No work has begun on this task yet.
- In Progress
- Work is underway but the completion criterion is not yet met.
- Complete
- The completion criterion has been met and supporting evidence has been reviewed. Do not mark a task Complete only because the activity occurred.
- Blocked
- The task cannot proceed. Record the blocker in Notes.
- Not Applicable
- Record the reason and the approving authority in Notes.
- Accepted Risk
- Record the accepting authority, the interim control and the review date in Notes.
Applicability legend
- Required
- This task applies to the project as scoped.
- Conditional
- Applicability depends on site, authority, technology, or scope decisions not yet made.
- Not Applicable
- Confirmed out of scope for this project — record the reason in Notes.
- To be assessed
- Applicability has not yet been evaluated for this project.
Priority (Critical, High, Medium, Low) and Applicability are always shown as text, never by colour alone.
The complete tracker — 60 tasks
Percent complete = Complete ÷ (Total − Not Applicable). Not Applicable tasks are removed from the denominator because they are out of scope; Accepted Risk tasks stay in the denominator but are never counted as complete, so accepted risk is always visible rather than hidden inside the percentage.
Loading saved progress…
| Task ID | Task | Phase | Workstream | Owner role | Depends on | Status | Priority | Applicability | Details |
|---|---|---|---|---|---|---|---|---|---|
| COM-001 | Appoint commissioning manager | Initiation | Governance | Project Director | — | Critical | To be assessed | ||
Show details for COM-001Hide details for COM-001Task Appoint commissioning manager Completion criteria Named manager has written authority over commissioning planning, testing coordination, defect governance and readiness reporting. Dependency explanation Starting task. Accountable role Project Director Owns end-to-end delivery, cross-workstream decisions, executive escalation and stage-gate readiness. Supporting roles PMO Lead; Operations Manager Evidence required Approved appointment or RACI Gate or milestone blocked Commissioning mobilisation Risk if delayed Fragmented testing and unresolved interface ownership. | |||||||||
| COM-002 | Appoint independent commissioning authority | Initiation | Governance | Project Director | High | Conditional | |||
Show details for COM-002Hide details for COM-002Task Appoint independent commissioning authority Completion criteria Independence, scope, deliverables, witness rights and reporting line are contractually defined. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Project Director Owns end-to-end delivery, cross-workstream decisions, executive escalation and stage-gate readiness. Supporting roles Procurement Lead; Commissioning Manager Evidence required Executed appointment and scope Gate or milestone blocked Commissioning plan approval Risk if delayed Testing may only prove vendor scope rather than end-to-end performance. | |||||||||
| COM-003 | Approve commissioning RACI and witness matrix | Planning | Governance | Commissioning Manager | Critical | To be assessed | |||
Show details for COM-003Hide details for COM-003Task Approve commissioning RACI and witness matrix Completion criteria Every system and test level has one accountable owner, required performers, reviewers, witnesses and final acceptor. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Commissioning Manager Owns commissioning strategy, test plans, witnesses, execution, defects, retests and evidence. Supporting roles Project Director; Commissioning Authority; Operations Manager; OEM or System Vendor Evidence required Approved RACI and witness matrix Gate or milestone blocked Test procedure release Risk if delayed Tests may be disputed or repeated because acceptance authority was unclear. | |||||||||
| COM-004 | Create systems and subsystem register | Planning | Scope | Commissioning Manager | Critical | To be assessed | |||
Show details for COM-004Hide details for COM-004Task Create systems and subsystem register Completion criteria All electrical, mechanical, fire, controls, telecom, security and supporting systems are uniquely identified and mapped to test levels. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Commissioning Manager Owns commissioning strategy, test plans, witnesses, execution, defects, retests and evidence. Supporting roles Design Manager; Document Controller Evidence required Controlled systems register Gate or milestone blocked Commissioning schedule baseline Risk if delayed Equipment or interfaces may escape testing. | |||||||||
| COM-005 | Define commissioning levels and acceptance pathway | Planning | Scope | Commissioning Authority | Critical | To be assessed | |||
Show details for COM-005Hide details for COM-005Task Define commissioning levels and acceptance pathway Completion criteria Project-specific levels from factory inspection through integrated systems testing and operations acceptance are approved. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Commissioning Authority Independently challenges test scope, witnesses critical tests and validates readiness and results. Supporting roles Commissioning Manager; Design Manager; Operations Manager Evidence required Approved commissioning strategy Gate or milestone blocked Commissioning plan approval Risk if delayed Stakeholders may confuse installation checks with operational proof. | |||||||||
| COM-006 | Create integrated commissioning schedule | Planning | Schedule | Commissioning Manager | Critical | To be assessed | |||
Show details for COM-006Hide details for COM-006Task Create integrated commissioning schedule Completion criteria Testing sequence includes prerequisites, resource loading, vendor attendance, witness dates, retests, contingency and handover milestones. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Commissioning Manager Owns commissioning strategy, test plans, witnesses, execution, defects, retests and evidence. Supporting roles PMO Lead; Construction Manager; OEM or System Vendor Evidence required Baselined commissioning schedule Gate or milestone blocked Test mobilisation Risk if delayed Late prerequisites or vendor conflicts can delay go-live. | |||||||||
| COM-007 | Approve commissioning safety plan | Planning | Safety | HSE Manager | Critical | To be assessed | |||
Show details for COM-007Hide details for COM-007Task Approve commissioning safety plan Completion criteria Permit-to-work, isolation, lockout/tagout, energisation boundaries, temporary systems, emergency response and stop-work authority are approved. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role HSE Manager Owns safety systems, permits, emergency controls, statutory safety records and test safety. Supporting roles Commissioning Manager; Construction Manager; Operations Manager Evidence required Approved safety plan and permits framework Gate or milestone blocked Energisation and live testing Risk if delayed Serious injury, equipment damage or unsafe test execution. | |||||||||
| COM-008 | Define defect severity and acceptance rules | Planning | Quality | Quality Manager | Critical | To be assessed | |||
Show details for COM-008Hide details for COM-008Task Define defect severity and acceptance rules Completion criteria Critical, high, medium and low defects have objective definitions, closure evidence, retest rules and authorised risk-acceptance levels. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Quality Manager Owns inspection plans, quality records, non-conformance, snag closure and evidence quality. Supporting roles Commissioning Authority; Project Director; Operations Manager Evidence required Approved defect and acceptance procedure Gate or milestone blocked Test execution Risk if delayed Defects may be closed subjectively or hidden at handover. | |||||||||
| COM-009 | Create commissioning evidence repository and naming convention | Planning | Evidence | Document Controller | High | To be assessed | |||
Show details for COM-009Hide details for COM-009Task Create commissioning evidence repository and naming convention Completion criteria Test procedures, readings, photos, logs, witness sheets, defects and retest evidence have controlled locations and traceable names. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Document Controller Owns document numbering, version control, repository completeness, transmittals and retrieval. Supporting roles Commissioning Manager; Quality Manager Evidence required Repository structure and document-control procedure Gate or milestone blocked First formal test Risk if delayed Evidence may be lost or impossible to audit. | |||||||||
| COM-010 | Create commissioning readiness checklist and review cadence | Planning | Readiness | Commissioning Manager | Critical | To be assessed | |||
Show details for COM-010Hide details for COM-010Task Create commissioning readiness checklist and review cadence Completion criteria A recurring review covers design, construction, utilities, test equipment, permits, vendors, documents, operations and open blockers. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Commissioning Manager Owns commissioning strategy, test plans, witnesses, execution, defects, retests and evidence. Supporting roles PMO Lead; Construction Manager; Operations Manager Evidence required Approved readiness checklist and meeting calendar Gate or milestone blocked System test release Risk if delayed Testing may start with unresolved prerequisites. | |||||||||
| COM-011 | Freeze commissioning design inputs | Design Readiness | Documentation | Design Manager | Critical | To be assessed | |||
Show details for COM-011Hide details for COM-011Task Freeze commissioning design inputs Completion criteria Latest approved owner requirements, basis of design, SLDs, P&IDs, sequences, cause-and-effect matrices and point lists are controlled. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Design Manager Coordinates multidisciplinary design, interfaces, reviews, change control and design freeze. Supporting roles Electrical Lead; Mechanical and Cooling Lead; Fire and Life Safety Consultant; Controls and Monitoring Lead Evidence required Commissioning design-input index Gate or milestone blocked Procedure development Risk if delayed Tests may validate superseded or inconsistent designs. | |||||||||
| COM-012 | Review design for testability and isolation | Design Readiness | Testability | Commissioning Authority | Critical | To be assessed | |||
Show details for COM-012Hide details for COM-012Task Review design for testability and isolation Completion criteria Required test points, meters, bypasses, isolation points, simulated inputs and safe failure injection methods are provided. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Commissioning Authority Independently challenges test scope, witnesses critical tests and validates readiness and results. Supporting roles Design Manager; Electrical Lead; Mechanical and Cooling Lead; Controls and Monitoring Lead Evidence required Testability review report and closed actions Gate or milestone blocked Design freeze / field modifications Risk if delayed Critical scenarios may be impossible to test safely. | |||||||||
| COM-013 | Verify contractual FAT, SAT, IST and support obligations | Procurement Readiness | Contracts | Procurement Lead | High | To be assessed | |||
Show details for COM-013Hide details for COM-013Task Verify contractual FAT, SAT, IST and support obligations Completion criteria Each relevant package specifies procedures, attendance, instruments, data, training, retesting, documentation and defect closure obligations. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Procurement Lead Owns sourcing, tendering, commercial closure, contractual obligations and supplier escalation. Supporting roles Commissioning Manager; Quality Manager; Legal Counsel Evidence required Contract compliance matrix Gate or milestone blocked Vendor manufacturing and mobilisation Risk if delayed Vendors may refuse tests or charge unplanned extras. | |||||||||
| COM-014 | Confirm calibrated test instruments and temporary infrastructure | Procurement Readiness | Resources | Commissioning Manager | Critical | To be assessed | |||
Show details for COM-014Hide details for COM-014Task Confirm calibrated test instruments and temporary infrastructure Completion criteria Instrument list, calibration certificates, load banks, cables, temporary cooling, fuel, water and communications are available for planned tests. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Commissioning Manager Owns commissioning strategy, test plans, witnesses, execution, defects, retests and evidence. Supporting roles OEM or System Vendor; HSE Manager; Quality Manager Evidence required Resource register and calibration certificates Gate or milestone blocked Test mobilisation Risk if delayed Invalid readings, unsafe temporary setup or cancelled tests. | |||||||||
| COM-015 | Confirm OEM and specialist attendance | Procurement Readiness | Vendors | Procurement Lead | High | To be assessed | |||
Show details for COM-015Hide details for COM-015Task Confirm OEM and specialist attendance Completion criteria Named competent representatives are booked for all tests requiring proprietary access, warranty presence or specialist diagnosis. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Procurement Lead Owns sourcing, tendering, commercial closure, contractual obligations and supplier escalation. Supporting roles Commissioning Manager; OEM or System Vendor Evidence required Confirmed attendance schedule Gate or milestone blocked System test execution Risk if delayed Tests may be delayed or warranties disputed. | |||||||||
| COM-016 | Approve FAT procedures | Factory Testing | FAT | Commissioning Authority | High | To be assessed | |||
Show details for COM-016Hide details for COM-016Task Approve FAT procedures Completion criteria Procedures state scope, prerequisites, steps, instruments, acceptance limits, evidence, hold points and defect handling. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Commissioning Authority Independently challenges test scope, witnesses critical tests and validates readiness and results. Supporting roles Commissioning Manager; Quality Manager; OEM or System Vendor Evidence required Approved FAT procedure Gate or milestone blocked Factory acceptance testing Risk if delayed Factory tests may omit project-specific requirements. | |||||||||
| COM-017 | Execute witnessed FAT for critical equipment | Factory Testing | FAT | OEM or System Vendor | High | To be assessed | |||
Show details for COM-017Hide details for COM-017Task Execute witnessed FAT for critical equipment Completion criteria Approved tests are completed, readings recorded, witnesses sign and all deviations receive formal disposition. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role OEM or System Vendor Provides procedures, specialist resources, settings, test support, corrections and product evidence. Supporting roles Commissioning Manager; Commissioning Authority; Quality Manager Evidence required Signed FAT report and deviation log Gate or milestone blocked Shipment authorisation Risk if delayed Defective or non-compliant equipment may reach site. | |||||||||
| COM-018 | Close or transfer FAT defects | Factory Testing | FAT | Quality Manager | Critical | To be assessed | |||
Show details for COM-018Hide details for COM-018Task Close or transfer FAT defects Completion criteria Every FAT defect is closed before shipment or formally transferred with owner, due date, site retest and commercial protection. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Quality Manager Owns inspection plans, quality records, non-conformance, snag closure and evidence quality. Supporting roles Procurement Lead; Commissioning Manager; OEM or System Vendor Evidence required FAT defect closure register Gate or milestone blocked Shipment authorisation Risk if delayed Known defects may disappear between factory and site. | |||||||||
| COM-019 | Inspect equipment on receipt and verify preservation | Site Receipt | Delivery | Quality Manager | High | To be assessed | |||
Show details for COM-019Hide details for COM-019Task Inspect equipment on receipt and verify preservation Completion criteria Quantity, model, ratings, serial numbers, damage, storage and preservation comply with approved submittals and manufacturer requirements. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Quality Manager Owns inspection plans, quality records, non-conformance, snag closure and evidence quality. Supporting roles Construction Manager; OEM or System Vendor; Document Controller Evidence required Material receipt inspection report Gate or milestone blocked Installation release Risk if delayed Transit damage or wrong equipment may be installed. | |||||||||
| COM-020 | Complete installation quality inspections | Pre-commissioning | Installation | Quality Manager | Critical | To be assessed | |||
Show details for COM-020Hide details for COM-020Task Complete installation quality inspections Completion criteria Equipment location, clearances, supports, labels, terminations, earthing, torque, pipework and access comply with approved drawings. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Quality Manager Owns inspection plans, quality records, non-conformance, snag closure and evidence quality. Supporting roles Construction Manager; Electrical Lead; Mechanical and Cooling Lead Evidence required Signed inspection and test records Gate or milestone blocked Pre-commissioning release Risk if delayed Unsafe or defective installation may fail during live testing. | |||||||||
| COM-021 | Complete electrical pre-commissioning tests | Pre-commissioning | Electrical | Electrical Lead | Critical | To be assessed | |||
Show details for COM-021Hide details for COM-021Task Complete electrical pre-commissioning tests Completion criteria Insulation, continuity, earthing, phasing, protection wiring, interlocks, control power and equipment-specific checks pass. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Electrical Lead Owns electrical design, protection, utility interfaces, energisation readiness and electrical compliance. Supporting roles Commissioning Manager; Quality Manager; OEM or System Vendor Evidence required Electrical pre-commissioning test pack Gate or milestone blocked Energisation Risk if delayed Damage, protection failure or unsafe energisation. | |||||||||
| COM-022 | Complete mechanical pre-commissioning tests | Pre-commissioning | Mechanical | Mechanical and Cooling Lead | Critical | To be assessed | |||
Show details for COM-022Hide details for COM-022Task Complete mechanical pre-commissioning tests Completion criteria Pressure testing, flushing, cleaning, leak checks, alignment, rotation, valve verification, balancing prerequisites and water treatment pass. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Mechanical and Cooling Lead Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria. Supporting roles Commissioning Manager; Quality Manager; OEM or System Vendor Evidence required Mechanical pre-commissioning test pack Gate or milestone blocked Wet commissioning Risk if delayed Leaks, contamination or equipment damage. | |||||||||
| COM-023 | Complete point-to-point and sensor checks | Pre-commissioning | Controls | Controls and Monitoring Lead | Critical | To be assessed | |||
Show details for COM-023Hide details for COM-023Task Complete point-to-point and sensor checks Completion criteria Every required point has correct source, address, engineering units, scaling, status, alarm path and calibrated sensor reading. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Controls and Monitoring Lead Owns BMS/DCIM/EPMS points, sequences, alarms, integrations, access and reporting. Supporting roles Commissioning Manager; OEM or System Vendor; Quality Manager Evidence required Point-to-point sheets and calibration records Gate or milestone blocked Functional controls testing Risk if delayed Monitoring may display false states or miss critical alarms. | |||||||||
| COM-024 | Complete fire-system pre-functional checks | Pre-commissioning | Fire and Safety | Fire and Life Safety Consultant | Critical | To be assessed | |||
Show details for COM-024Hide details for COM-024Task Complete fire-system pre-functional checks Completion criteria Devices, loops, panels, interfaces, suppression readiness, pumps, emergency lighting and access-release prerequisites are verified. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Fire and Life Safety Consultant Owns the fire strategy, code interpretation, submissions, inspections and closure evidence. Supporting roles Commissioning Manager; Security Lead; Controls and Monitoring Lead Evidence required Fire pre-functional checklist Gate or milestone blocked Fire integrated testing Risk if delayed Life-safety functions may fail or create unsafe releases. | |||||||||
| COM-025 | Approve system energisation and test release | Pre-commissioning | Readiness | Commissioning Manager | Critical | To be assessed | |||
Show details for COM-025Hide details for COM-025Task Approve system energisation and test release Completion criteria Construction completion, approved procedures, permits, personnel, instruments, utilities and open-defect thresholds satisfy release criteria. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Commissioning Manager Owns commissioning strategy, test plans, witnesses, execution, defects, retests and evidence. Supporting roles HSE Manager; Quality Manager; Operations Manager; Commissioning Authority Evidence required Signed test-release certificate Gate or milestone blocked Functional testing Risk if delayed Premature testing can injure personnel or damage equipment. | |||||||||
| COM-026 | Test utility, transformer and switchgear functions | Functional Testing | Utility and HV | Electrical Lead | Critical | To be assessed | |||
Show details for COM-026Hide details for COM-026Task Test utility, transformer and switchgear functions Completion criteria Normal operation, protection, interlocks, metering, alarms and safe isolation perform within approved limits. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Electrical Lead Owns electrical design, protection, utility interfaces, energisation readiness and electrical compliance. Supporting roles Commissioning Manager; Utility Liaison Lead; OEM or System Vendor Evidence required Signed functional test reports and relay records Gate or milestone blocked Electrical path acceptance Risk if delayed Upstream faults or incorrect protection can disable the facility. | |||||||||
| COM-027 | Test UPS normal, bypass, module failure and battery functions | Functional Testing | UPS and Batteries | Electrical Lead | Critical | To be assessed | |||
Show details for COM-027Hide details for COM-027Task Test UPS normal, bypass, module failure and battery functions Completion criteria Normal mode, static bypass, maintenance bypass, module loss, alarms, battery monitoring and specified autonomy/discharge tests pass. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Electrical Lead Owns electrical design, protection, utility interfaces, energisation readiness and electrical compliance. Supporting roles Commissioning Manager; OEM or System Vendor; Operations Manager Evidence required UPS and battery test report Gate or milestone blocked Critical power acceptance Risk if delayed Critical loads may drop or batteries may underperform. | |||||||||
| COM-028 | Test generator start, loading, synchronisation and controls | Functional Testing | Generators | Electrical Lead | Critical | To be assessed | |||
Show details for COM-028Hide details for COM-028Task Test generator start, loading, synchronisation and controls Completion criteria Automatic/manual start, step loads, load acceptance, synchronisation where applicable, alarms, fuel controls and shutdown protections pass. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Electrical Lead Owns electrical design, protection, utility interfaces, energisation readiness and electrical compliance. Supporting roles Commissioning Manager; OEM or System Vendor; Facilities Manager Evidence required Generator functional and load test report Gate or milestone blocked Backup power acceptance Risk if delayed Facility may not sustain utility failure. | |||||||||
| COM-029 | Test ATS, STS and transfer sequences | Functional Testing | Transfer Systems | Electrical Lead | Critical | To be assessed | |||
Show details for COM-029Hide details for COM-029Task Test ATS, STS and transfer sequences Completion criteria Transfers occur within approved limits without unsafe overlap, incorrect source selection or unacceptable downstream disturbance. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Electrical Lead Owns electrical design, protection, utility interfaces, energisation readiness and electrical compliance. Supporting roles Commissioning Manager; OEM or System Vendor; Operations Manager Evidence required Transfer-system test report and waveforms Gate or milestone blocked Electrical integrated testing Risk if delayed Critical loads may interrupt during source transitions. | |||||||||
| COM-030 | Test downstream distribution and metering | Functional Testing | Distribution | Electrical Lead | High | To be assessed | |||
Show details for COM-030Hide details for COM-030Task Test downstream distribution and metering Completion criteria Busduct, PDUs, RPPs and relevant branch circuits show correct phasing, protection, metering, alarms and identification. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Electrical Lead Owns electrical design, protection, utility interfaces, energisation readiness and electrical compliance. Supporting roles Commissioning Manager; Quality Manager; Controls and Monitoring Lead Evidence required Distribution test pack Gate or milestone blocked Load-bank connection / rack energisation Risk if delayed Hidden distribution defects can affect only part of the IT load. | |||||||||
| COM-031 | Test chillers or primary cooling equipment | Functional Testing | Primary Cooling | Mechanical and Cooling Lead | Critical | To be assessed | |||
Show details for COM-031Hide details for COM-031Task Test chillers or primary cooling equipment Completion criteria Capacity, controls, safeties, alarms, restart, part-load behaviour and manufacturer performance checks pass. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Mechanical and Cooling Lead Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria. Supporting roles Commissioning Manager; OEM or System Vendor; Controls and Monitoring Lead Evidence required Primary cooling functional test report Gate or milestone blocked Cooling-system acceptance Risk if delayed Cooling capacity or recovery may be inadequate. | |||||||||
| COM-032 | Test pumps, valves, flow and isolation | Functional Testing | Hydraulics | Mechanical and Cooling Lead | Critical | To be assessed | |||
Show details for COM-032Hide details for COM-032Task Test pumps, valves, flow and isolation Completion criteria Duty/standby operation, flow, pressure, valve actuation, lead-lag rotation, safe isolation and balancing meet design. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Mechanical and Cooling Lead Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria. Supporting roles Commissioning Manager; OEM or System Vendor; Facilities Manager Evidence required Hydraulic functional and balancing report Gate or milestone blocked Cooling integrated testing Risk if delayed A common hydraulic fault may defeat installed redundancy. | |||||||||
| COM-033 | Test CRAH, CRAC and terminal cooling units | Functional Testing | Terminal Cooling | Mechanical and Cooling Lead | Critical | To be assessed | |||
Show details for COM-033Hide details for COM-033Task Test CRAH, CRAC and terminal cooling units Completion criteria Airflow, temperature control, fan response, alarms, restart, redundancy and loss-of-unit behaviour pass. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Mechanical and Cooling Lead Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria. Supporting roles Commissioning Manager; Controls and Monitoring Lead; OEM or System Vendor Evidence required Terminal cooling test report Gate or milestone blocked Thermal load testing Risk if delayed Rack environments may overheat despite plant capacity. | |||||||||
| COM-034 | Test make-up water, treatment, storage and leak detection | Functional Testing | Water Systems | Water and Environmental Lead | High | To be assessed | |||
Show details for COM-034Hide details for COM-034Task Test make-up water, treatment, storage and leak detection Completion criteria Level controls, treatment, quality, replenishment, low-water alarms, leak detection and isolation perform as designed. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Water and Environmental Lead Owns water balance, source legality, quality, treatment, discharge and environmental obligations. Supporting roles Mechanical and Cooling Lead; Commissioning Manager; Facilities Manager Evidence required Water-system and leak-detection test report Gate or milestone blocked Cooling resilience acceptance Risk if delayed Water failure or leak may disable cooling or damage IT equipment. | |||||||||
| COM-035 | Test cooling sequences and recovery | Functional Testing | Cooling Controls | Controls and Monitoring Lead | Critical | To be assessed | |||
Show details for COM-035Hide details for COM-035Task Test cooling sequences and recovery Completion criteria Lead-lag, staging, failover, high-temperature response, control failure and post-power-loss recovery follow approved sequence. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Controls and Monitoring Lead Owns BMS/DCIM/EPMS points, sequences, alarms, integrations, access and reporting. Supporting roles Mechanical and Cooling Lead; Commissioning Manager; Operations Manager Evidence required Cooling sequence test report Gate or milestone blocked Cooling integrated testing Risk if delayed Controls may create cascading failure even when equipment is healthy. | |||||||||
| COM-036 | Test detection, alarm, suppression and cause-and-effect | Functional Testing | Fire and Life Safety | Fire and Life Safety Consultant | Critical | To be assessed | |||
Show details for COM-036Hide details for COM-036Task Test detection, alarm, suppression and cause-and-effect Completion criteria Approved cause-and-effect responses, annunciation, shutdowns, dampers, releases, emergency lighting and interfaces pass. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Fire and Life Safety Consultant Owns the fire strategy, code interpretation, submissions, inspections and closure evidence. Supporting roles Commissioning Manager; Security Lead; Controls and Monitoring Lead; Operations Manager Evidence required Signed fire functional and cause-and-effect test report Gate or milestone blocked Life-safety acceptance Risk if delayed Unsafe evacuation, failed suppression or unintended shutdown. | |||||||||
| COM-037 | Validate monitoring, alarms, trends and access controls | Functional Testing | BMS DCIM EPMS | Controls and Monitoring Lead | Critical | To be assessed | |||
Show details for COM-037Hide details for COM-037Task Validate monitoring, alarms, trends and access controls Completion criteria Points, thresholds, severity, routing, escalation, timestamps, dashboards, trends, reports, user roles and audit logs are correct. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Controls and Monitoring Lead Owns BMS/DCIM/EPMS points, sequences, alarms, integrations, access and reporting. Supporting roles Commissioning Manager; Operations Manager; Security Lead Evidence required Monitoring validation report and alarm matrix Gate or milestone blocked Operations monitoring acceptance Risk if delayed Operations may not detect or diagnose failures. | |||||||||
| COM-038 | Test carrier handoffs, fibre paths and failover | Functional Testing | Telecom | Telecom Lead | High | To be assessed | |||
Show details for COM-038Hide details for COM-038Task Test carrier handoffs, fibre paths and failover Completion criteria Handoffs, cross-connects, labelling, bandwidth, latency, route diversity and required path failover meet requirements. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Telecom Lead Owns carrier strategy, physical route diversity, right-of-way, building entry and service acceptance. Supporting roles IT and Network Lead; Commissioning Manager; Operations Manager Evidence required Telecom acceptance test report and route evidence Gate or milestone blocked Network service readiness Risk if delayed Facility may have nominal dual carriers but shared physical failure. | |||||||||
| COM-039 | Test access control, CCTV, visitor and emergency behaviour | Functional Testing | Physical Security | Security Lead | High | To be assessed | |||
Show details for COM-039Hide details for COM-039Task Test access control, CCTV, visitor and emergency behaviour Completion criteria Readers, doors, mantraps, CCTV, retention, visitor flows, emergency releases, overrides and audit logs work as approved. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Security Lead Owns physical security design, access control, CCTV, security procedures and incident escalation. Supporting roles Commissioning Manager; Controls and Monitoring Lead; Operations Manager Evidence required Security systems acceptance report Gate or milestone blocked Security operations readiness Risk if delayed Unauthorised access or failed emergency egress. | |||||||||
| COM-040 | Approve load-bank and thermal-test plan | Integrated Testing | Load Bank | Commissioning Authority | Critical | To be assessed | |||
Show details for COM-040Hide details for COM-040Task Approve load-bank and thermal-test plan Completion criteria Load level, duration, ramp profile, placement, heat rejection, instruments, safety, witness and abort criteria are approved. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Commissioning Authority Independently challenges test scope, witnesses critical tests and validates readiness and results. Supporting roles Commissioning Manager; HSE Manager; Electrical Lead; Mechanical and Cooling Lead Evidence required Approved load-bank plan and risk assessment Gate or milestone blocked Load-bank mobilisation Risk if delayed Test may be unsafe or fail to represent real operating conditions. | |||||||||
| COM-041 | Execute staged electrical and thermal load test | Integrated Testing | Load Bank | Commissioning Manager | Critical | To be assessed | |||
Show details for COM-041Hide details for COM-041Task Execute staged electrical and thermal load test Completion criteria Approved loads and durations are achieved; power quality, temperatures, flows, alarms, capacity and stability remain within limits. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Commissioning Manager Owns commissioning strategy, test plans, witnesses, execution, defects, retests and evidence. Supporting roles Electrical Lead; Mechanical and Cooling Lead; Commissioning Authority; Operations Manager Evidence required Signed load-bank report, readings and trend exports Gate or milestone blocked Integrated systems testing Risk if delayed Facility performance under realistic load remains unproven. | |||||||||
| COM-042 | Approve integrated systems test scripts | Integrated Testing | IST Planning | Commissioning Authority | Critical | To be assessed | |||
Show details for COM-042Hide details for COM-042Task Approve integrated systems test scripts Completion criteria Each script states initial condition, injected failure, expected sequence, alarm, operator action, recovery, acceptance and rollback. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Commissioning Authority Independently challenges test scope, witnesses critical tests and validates readiness and results. Supporting roles Commissioning Manager; Operations Manager; HSE Manager Evidence required Approved IST scripts Gate or milestone blocked IST execution Risk if delayed Failure testing may be ad hoc and unsafe. | |||||||||
| COM-043 | Test utility loss and generator recovery | Integrated Testing | Power Failure Scenarios | Commissioning Manager | Critical | To be assessed | |||
Show details for COM-043Hide details for COM-043Task Test utility loss and generator recovery Completion criteria Utility loss is detected; UPS supports load; generators start and accept load; transfers, alarms and restoration follow design. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Commissioning Manager Owns commissioning strategy, test plans, witnesses, execution, defects, retests and evidence. Supporting roles Electrical Lead; Operations Manager; Commissioning Authority Evidence required Signed utility-loss IST report Gate or milestone blocked Resilience acceptance Risk if delayed Core backup-power architecture is unproven. | |||||||||
| COM-044 | Test generator start failure and reduced redundancy | Integrated Testing | Power Failure Scenarios | Commissioning Manager | Critical | To be assessed | |||
Show details for COM-044Hide details for COM-044Task Test generator start failure and reduced redundancy Completion criteria Failed start or unavailable generator produces correct alarms, remaining capacity response, operator escalation and safe recovery. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Commissioning Manager Owns commissioning strategy, test plans, witnesses, execution, defects, retests and evidence. Supporting roles Electrical Lead; Facilities Manager; Operations Manager Evidence required Signed generator-failure IST report Gate or milestone blocked Resilience acceptance Risk if delayed N+1 assumptions may not survive a real failure. | |||||||||
| COM-045 | Test UPS module or power-path failure | Integrated Testing | Power Failure Scenarios | Commissioning Manager | Critical | To be assessed | |||
Show details for COM-045Hide details for COM-045Task Test UPS module or power-path failure Completion criteria Failure is isolated, load remains supported within design intent, alarms route correctly and recovery does not introduce further risk. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Commissioning Manager Owns commissioning strategy, test plans, witnesses, execution, defects, retests and evidence. Supporting roles Electrical Lead; Operations Manager; Commissioning Authority Evidence required Signed UPS/path-failure IST report Gate or milestone blocked Critical power acceptance Risk if delayed A hidden common-mode or transfer defect may drop IT load. | |||||||||
| COM-046 | Test cooling-unit, pump and control failures | Integrated Testing | Cooling Failure Scenarios | Commissioning Manager | Critical | To be assessed | |||
Show details for COM-046Hide details for COM-046Task Test cooling-unit, pump and control failures Completion criteria Specified component failures maintain acceptable environment, trigger correct alarms and allow safe operator intervention and recovery. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Commissioning Manager Owns commissioning strategy, test plans, witnesses, execution, defects, retests and evidence. Supporting roles Mechanical and Cooling Lead; Controls and Monitoring Lead; Operations Manager Evidence required Signed cooling-failure IST reports Gate or milestone blocked Cooling resilience acceptance Risk if delayed Installed redundancy may not operate as a system. | |||||||||
| COM-047 | Test high-temperature and water-leak response | Integrated Testing | Environmental Scenarios | Commissioning Manager | Critical | To be assessed | |||
Show details for COM-047Hide details for COM-047Task Test high-temperature and water-leak response Completion criteria Detection, alarm, escalation, containment, isolation, operator response and recovery meet approved procedures. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Commissioning Manager Owns commissioning strategy, test plans, witnesses, execution, defects, retests and evidence. Supporting roles Mechanical and Cooling Lead; Water and Environmental Lead; Operations Manager Evidence required Signed environmental incident test reports Gate or milestone blocked Environmental resilience acceptance Risk if delayed Slow response can damage IT equipment or prolong outage. | |||||||||
| COM-048 | Test BMS, DCIM or communications failure | Integrated Testing | Monitoring Failure Scenarios | Controls and Monitoring Lead | High | To be assessed | |||
Show details for COM-048Hide details for COM-048Task Test BMS, DCIM or communications failure Completion criteria Monitoring loss is detected, fallback monitoring and manual response are usable, and service restores without lost configuration. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Controls and Monitoring Lead Owns BMS/DCIM/EPMS points, sequences, alarms, integrations, access and reporting. Supporting roles Commissioning Manager; Operations Manager; IT and Network Lead Evidence required Signed monitoring-failure test report Gate or milestone blocked Operations acceptance Risk if delayed A facility can be technically healthy but operationally blind. | |||||||||
| COM-049 | Test fire event interfaces under operating conditions | Integrated Testing | Fire Interface Scenario | Fire and Life Safety Consultant | Critical | To be assessed | |||
Show details for COM-049Hide details for COM-049Task Test fire event interfaces under operating conditions Completion criteria Alarm, suppression interfaces, shutdowns, access release, communications and operator actions follow approved cause-and-effect. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Fire and Life Safety Consultant Owns the fire strategy, code interpretation, submissions, inspections and closure evidence. Supporting roles Commissioning Manager; Security Lead; Operations Manager Evidence required Signed fire IST report Gate or milestone blocked Life-safety and operating acceptance Risk if delayed Cross-system response may endanger people or unnecessarily disable critical systems. | |||||||||
| COM-050 | Test required network path failure and recovery | Integrated Testing | Network Failure Scenario | IT and Network Lead | High | To be assessed | |||
Show details for COM-050Hide details for COM-050Task Test required network path failure and recovery Completion criteria Traffic uses approved alternate path, alarms identify the event, service remains within requirements and normal state is safely restored. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role IT and Network Lead Owns network services, management connectivity, access, telemetry and technology readiness. Supporting roles Telecom Lead; Commissioning Manager; Operations Manager Evidence required Signed network failover test report Gate or milestone blocked Connectivity acceptance Risk if delayed Physical or logical diversity may be ineffective. | |||||||||
| COM-051 | Measure operations response during IST | Integrated Testing | Operations Response | Operations Manager | Critical | To be assessed | |||
Show details for COM-051Hide details for COM-051Task Measure operations response during IST Completion criteria For each scenario, detection, acknowledgement, escalation, diagnosis, stabilisation, communication and recovery times are recorded. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Operations Manager Owns operational acceptance, staffing, procedures, monitoring, maintenance and post-handover accountability. Supporting roles Commissioning Manager; PMO Lead Evidence required Operations response scorecard Gate or milestone blocked Operations readiness gate Risk if delayed Systems may pass while the operating team remains unprepared. | |||||||||
| COM-052 | Maintain controlled commissioning defect register | Defect Closure | Governance | Quality Manager | Critical | To be assessed | |||
Show details for COM-052Hide details for COM-052Task Maintain controlled commissioning defect register Completion criteria Every observation has unique ID, severity, owner, due date, system, root cause, action, evidence, retest and acceptance status. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Quality Manager Owns inspection plans, quality records, non-conformance, snag closure and evidence quality. Supporting roles Commissioning Manager; Document Controller; OEM or System Vendor Evidence required Current controlled defect register Gate or milestone blocked Every acceptance gate Risk if delayed Defects can be lost, downgraded or closed without proof. | |||||||||
| COM-053 | Perform root-cause analysis for critical and repeated failures | Defect Closure | Root Cause | Quality Manager | High | To be assessed | |||
Show details for COM-053Hide details for COM-053Task Perform root-cause analysis for critical and repeated failures Completion criteria Analysis identifies technical and process cause, affected systems, corrective action and prevention of recurrence. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Quality Manager Owns inspection plans, quality records, non-conformance, snag closure and evidence quality. Supporting roles Commissioning Authority; OEM or System Vendor; Design Manager Evidence required Approved root-cause reports Gate or milestone blocked Critical defect closure Risk if delayed Symptoms may be repaired while systemic defects remain. | |||||||||
| COM-054 | Retest corrected defects and affected interfaces | Defect Closure | Retest | Commissioning Manager | Critical | To be assessed | |||
Show details for COM-054Hide details for COM-054Task Retest corrected defects and affected interfaces Completion criteria Original failed test and required regression tests pass with new evidence and authorised witness acceptance. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Commissioning Manager Owns commissioning strategy, test plans, witnesses, execution, defects, retests and evidence. Supporting roles Quality Manager; Commissioning Authority; Operations Manager Evidence required Signed retest and regression evidence Gate or milestone blocked Commissioning acceptance Risk if delayed A fix may create a new failure elsewhere. | |||||||||
| COM-055 | Compile complete commissioning dossier | Documentation | Handover Evidence | Document Controller | Critical | To be assessed | |||
Show details for COM-055Hide details for COM-055Task Compile complete commissioning dossier Completion criteria FAT, SAT, pre-functional, functional, load-bank, IST, witness, defect, retest, settings and trend records are indexed and complete. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Document Controller Owns document numbering, version control, repository completeness, transmittals and retrieval. Supporting roles Commissioning Manager; Quality Manager Evidence required Controlled commissioning dossier index Gate or milestone blocked Commissioning acceptance Risk if delayed Facility behaviour cannot be audited or reproduced. | |||||||||
| COM-056 | Train operations using tested system behaviour | Operations Readiness | Training | Operations Manager | Critical | To be assessed | |||
Show details for COM-056Hide details for COM-056Task Train operations using tested system behaviour Completion criteria Operations personnel understand normal states, alarms, bypasses, failure sequences, procedures and escalation; competency is assessed. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Operations Manager Owns operational acceptance, staffing, procedures, monitoring, maintenance and post-handover accountability. Supporting roles Commissioning Manager; HR and Training Lead; OEM or System Vendor Evidence required Training records and competency assessment Gate or milestone blocked Operations acceptance Risk if delayed Staff may respond incorrectly despite successful technical tests. | |||||||||
| COM-057 | Reconcile SOPs, MOPs and EOPs with commissioning findings | Operations Readiness | Procedures | Operations Manager | Critical | To be assessed | |||
Show details for COM-057Hide details for COM-057Task Reconcile SOPs, MOPs and EOPs with commissioning findings Completion criteria Procedures reflect final as-built topology, tested sequences, alarm names, limits, precautions, rollback and lessons learned. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Operations Manager Owns operational acceptance, staffing, procedures, monitoring, maintenance and post-handover accountability. Supporting roles Commissioning Manager; Document Controller; HSE Manager Evidence required Approved final procedures and revision record Gate or milestone blocked Operations acceptance Risk if delayed Procedures may contradict actual system behaviour. | |||||||||
| COM-058 | Review residual commissioning risks | Acceptance | Risk | Project Director | Critical | To be assessed | |||
Show details for COM-058Hide details for COM-058Task Review residual commissioning risks Completion criteria All open items have severity, operational impact, interim control, accountable owner, due date and authorised acceptance level. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Project Director Owns end-to-end delivery, cross-workstream decisions, executive escalation and stage-gate readiness. Supporting roles Commissioning Authority; Quality Manager; Operations Manager; Executive Sponsor Evidence required Residual-risk and open-item acceptance register Gate or milestone blocked Commissioning acceptance Risk if delayed Go-live may proceed with unknown or ownerless risk. | |||||||||
| COM-059 | Approve commissioning acceptance | Acceptance | Final Gate | Project Director | Critical | To be assessed | |||
Show details for COM-059Hide details for COM-059Task Approve commissioning acceptance Completion criteria All safety-critical tests pass; critical defects close; required IST completes; evidence is complete; residual risks are authorised. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Project Director Owns end-to-end delivery, cross-workstream decisions, executive escalation and stage-gate readiness. Supporting roles Commissioning Authority; Operations Manager; Executive Sponsor Evidence required Signed commissioning acceptance certificate Gate or milestone blocked Operations handover and go-live Risk if delayed Unproven systems may be handed over as complete. | |||||||||
| COM-060 | Complete post-commissioning stabilisation review | Post-acceptance | Stabilisation | Operations Manager | High | To be assessed | |||
Show details for COM-060Hide details for COM-060Task Complete post-commissioning stabilisation review Completion criteria Early operating alarms, defects, trends and capacity are reviewed; corrective actions and final lessons learned are assigned. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Operations Manager Owns operational acceptance, staffing, procedures, monitoring, maintenance and post-handover accountability. Supporting roles Commissioning Manager; Quality Manager; PMO Lead Evidence required Stabilisation report and action register Gate or milestone blocked Final project close-out Risk if delayed Latent defects and recurring nuisance alarms may persist. | |||||||||