Data Center Project Management

Data Center Site Selection Scorecard — India

Requirements, legal diligence, constructability, power, water, climate, fibre, approvals, security, operations, and lifecycle cost inputs for a defensible site-selection decision.

Source article: Data Center Site Selection in India·
Share
49
Total tasks
32
Critical tasks
18
Phases
48
Workstreams
20
Accountable owner roles
This checklist is a project-management framework, not legal, regulatory, engineering or certification advice. Exact requirements vary by location, authority, facility design, operating model and project objectives. Validate applicability with qualified local professionals and the relevant authorities. Completing the checklist does not guarantee approval, certification, uptime or regulatory compliance.

How to use this tracker

Each row is an executable work package. Assign a named individual against the accountable role, enter planned start and end dates, follow the predecessor task IDs, and mark a task complete only when its completion criterion is met and supporting evidence has been reviewed.

The owner column deliberately contains the accountable role, not a person’s name, so the tracker stays reusable across organisations. Add a Named_Ownercolumn — or use the local “Named owner” field on each task below — in your working copy.

Using it in Excel

  1. Import the file as UTF-8.
  2. Convert the imported range into an Excel Table.
  3. Freeze the header row.
  4. Use ISO dates in YYYY-MM-DD format.
  5. Add data-validation lists for Status and Applicability.
  6. Filter Critical tasks and blocked project gates during every project review.
  7. Add a Named_Owner column in the working copy.
  8. Record the accepting authority in Notes for Accepted Risk.
  9. Preserve stable Task IDs when customising the tracker.
  10. Do not mark a task complete until its evidence has been reviewed.

Status legend

Not Started
No work has begun on this task yet.
In Progress
Work is underway but the completion criterion is not yet met.
Complete
The completion criterion has been met and supporting evidence has been reviewed. Do not mark a task Complete only because the activity occurred.
Blocked
The task cannot proceed. Record the blocker in Notes.
Not Applicable
Record the reason and the approving authority in Notes.
Accepted Risk
Record the accepting authority, the interim control and the review date in Notes.

Applicability legend

Required
This task applies to the project as scoped.
Conditional
Applicability depends on site, authority, technology, or scope decisions not yet made.
Not Applicable
Confirmed out of scope for this project — record the reason in Notes.
To be assessed
Applicability has not yet been evaluated for this project.

Priority (Critical, High, Medium, Low) and Applicability are always shown as text, never by colour alone.

The complete tracker — 49 tasks

0 / 49
Complete
0%
Percent complete
32
Critical open
0
Blocked
0
Not Applicable (excluded from %)
0
Accepted Risk (open, not counted complete)
48
Tasks with unmet predecessors
49 of 49
Showing

Percent complete = Complete ÷ (Total − Not Applicable). Not Applicable tasks are removed from the denominator because they are out of scope; Accepted Risk tasks stay in the denominator but are never counted as complete, so accepted risk is always visible rather than hidden inside the percentage.

Download blank CSV

Loading saved progress…

Task IDTaskPhaseWorkstreamOwner roleDepends onStatusPriorityApplicabilityDetails
SIT-001Appoint site selection lead and decision committeeInitiationGovernanceProject DirectorCriticalTo be assessed
Show details for SIT-001
Task
Appoint site selection lead and decision committee
Completion criteria
Named lead, technical reviewers, commercial reviewers and final decision authority are documented.
Dependency explanation
Starting task.
Accountable role
Project Director
Owns end-to-end delivery, cross-workstream decisions, executive escalation and stage-gate readiness.
Supporting roles
Executive Sponsor; Site Selection Lead; PMO Lead
Evidence required
Approved governance and RACI
Gate or milestone blocked
Site selection mobilisation
Risk if delayed
Site choice may be driven by one discipline or informal preference.
SIT-002Approve site selection requirementsInitiationRequirementsSite Selection Lead
CriticalTo be assessed
Show details for SIT-002
Task
Approve site selection requirements
Completion criteria
Day-one/full-build IT load, rack density, availability, latency, security, certification, schedule and expansion needs are approved.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Site Selection Lead
Owns candidate comparison, evidence pack, scoring, fatal-flaw analysis and recommendation.
Supporting roles
Electrical Lead; Mechanical and Cooling Lead; Telecom Lead; Operations Manager
Evidence required
Approved site requirements brief
Gate or milestone blocked
Longlist creation
Risk if delayed
Sites may be compared against shifting or incomplete requirements.
SIT-003Approve weighted scoring and fatal-flaw rulesInitiationScoringSite Selection Lead
CriticalTo be assessed
Show details for SIT-003
Task
Approve weighted scoring and fatal-flaw rules
Completion criteria
Weights, 1–5 score definitions, evidence standard, N/V treatment and non-negotiable rejection conditions are approved.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Site Selection Lead
Owns candidate comparison, evidence pack, scoring, fatal-flaw analysis and recommendation.
Supporting roles
Project Director; Insurance and Risk Lead; Finance and Commercial Lead
Evidence required
Approved scorecard methodology
Gate or milestone blocked
Site screening
Risk if delayed
A high average score may hide a fatal legal or utility flaw.
SIT-004Create site longlist and data-room requestScreeningPipelineSite Selection Lead
HighTo be assessed
Show details for SIT-004
Task
Create site longlist and data-room request
Completion criteria
Candidate sites are logged with owner, location, parcel details, contacts and standard evidence request.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Site Selection Lead
Owns candidate comparison, evidence pack, scoring, fatal-flaw analysis and recommendation.
Supporting roles
Land Due Diligence Lead; Document Controller
Evidence required
Longlist and data request pack
Gate or milestone blocked
Desktop screening
Risk if delayed
Comparisons may use inconsistent information.
SIT-005Obtain ownership and title documentsDesktop ScreeningLand and LegalLand Due Diligence Lead
CriticalTo be assessed
Show details for SIT-005
Task
Obtain ownership and title documents
Completion criteria
Current ownership, title chain, encumbrance records, survey and available legal documents are received for each candidate.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Land Due Diligence Lead
Coordinates title, survey, zoning, easement and access diligence for the site.
Supporting roles
Legal Counsel; Document Controller
Evidence required
Candidate legal data-room index
Gate or milestone blocked
Legal diligence
Risk if delayed
No reliable basis for site commitment.
SIT-006Verify title, encumbrance and litigation statusDue DiligenceLand and LegalLegal Counsel
CriticalTo be assessed
Show details for SIT-006
Task
Verify title, encumbrance and litigation status
Completion criteria
Independent legal review identifies ownership gaps, liens, disputes, acquisition notices and required cures.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Legal Counsel
Validates title, contracts, statutory interpretation, legal exposure and formal legal conclusions.
Supporting roles
Land Due Diligence Lead; Insurance and Risk Lead
Evidence required
Signed legal title memorandum
Gate or milestone blocked
Site shortlist / commercial commitment
Risk if delayed
Disputed or encumbered land can strand the project.
SIT-007Verify permitted use, zoning and conversion pathDue DiligenceLand UseLegal Counsel
CriticalTo be assessed
Show details for SIT-007
Task
Verify permitted use, zoning and conversion path
Completion criteria
Applicable zoning, land-use permission, conversion steps, restrictions and expected timeline are confirmed in writing.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Legal Counsel
Validates title, contracts, statutory interpretation, legal exposure and formal legal conclusions.
Supporting roles
Lead Architect; Approvals Manager; Land Due Diligence Lead
Evidence required
Land-use and zoning memorandum
Gate or milestone blocked
Site shortlist
Risk if delayed
Facility may not be legally constructible or operable.
SIT-008Verify survey, boundaries, easements and access rightsDue DiligenceBoundaries and RightsLand Due Diligence Lead
CriticalTo be assessed
Show details for SIT-008
Task
Verify survey, boundaries, easements and access rights
Completion criteria
Physical survey matches documents; access road, utility corridors, third-party rights and encroachments are mapped.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Land Due Diligence Lead
Coordinates title, survey, zoning, easement and access diligence for the site.
Supporting roles
Legal Counsel; Civil and Structural Lead
Evidence required
Certified survey and rights map
Gate or milestone blocked
Concept layout / transaction
Risk if delayed
Usable area or utility access may be less than represented.
SIT-009Assess lease or purchase terms and long-term controlDue DiligenceCommercial TermsLegal Counsel
HighTo be assessed
Show details for SIT-009
Task
Assess lease or purchase terms and long-term control
Completion criteria
Tenure, renewal, escalation, development rights, lender rights, access, assignment, expansion and termination risks are evaluated.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Legal Counsel
Validates title, contracts, statutory interpretation, legal exposure and formal legal conclusions.
Supporting roles
Finance and Commercial Lead; Project Director
Evidence required
Commercial legal risk memo
Gate or milestone blocked
Commercial negotiation
Risk if delayed
Weak tenure can undermine a long-life infrastructure investment.
SIT-010Complete topographical and physical site surveyTechnical DiligenceSite SurveyCivil and Structural Lead
HighTo be assessed
Show details for SIT-010
Task
Complete topographical and physical site survey
Completion criteria
Levels, slopes, existing structures, utilities, trees, drainage, access and constraints are surveyed and georeferenced.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Civil and Structural Lead
Owns civil, structural, drainage, grading, constructability and structural compliance.
Supporting roles
Site Selection Lead; Lead Architect
Evidence required
Topographical survey and constraint plan
Gate or milestone blocked
Concept layout
Risk if delayed
Hidden grading or demolition work may inflate cost and schedule.
SIT-011Complete geotechnical investigationTechnical DiligenceGeotechnicalGeotechnical Consultant
CriticalTo be assessed
Show details for SIT-011
Task
Complete geotechnical investigation
Completion criteria
Soil bearing, settlement, groundwater, excavation, contamination and foundation recommendations are documented.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Geotechnical Consultant
Owns subsurface investigation, bearing, settlement, seismic and geotechnical conclusions.
Supporting roles
Civil and Structural Lead; Insurance and Risk Lead
Evidence required
Geotechnical report
Gate or milestone blocked
Civil design and cost estimate
Risk if delayed
Foundation risk can materially change viability.
SIT-012Verify construction and heavy-equipment accessTechnical DiligenceAccessConstruction Manager
CriticalTo be assessed
Show details for SIT-012
Task
Verify construction and heavy-equipment access
Completion criteria
Road width, turning radii, bridges, culverts, overhead restrictions, monsoon access and delivery routes support planned equipment.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Construction Manager
Owns site execution, sequencing, contractor interfaces, installation readiness and completion.
Supporting roles
Civil and Structural Lead; Procurement Lead; HSE Manager
Evidence required
Heavy haul route survey
Gate or milestone blocked
Site shortlist / logistics plan
Risk if delayed
Transformers, generators or chillers may not reach the site.
SIT-013Verify emergency and operational accessTechnical DiligenceEmergency AccessHSE Manager
HighTo be assessed
Show details for SIT-013
Task
Verify emergency and operational access
Completion criteria
Fire, ambulance, police, fuel, maintenance and staff access remain practical during peak traffic and adverse weather.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
HSE Manager
Owns safety systems, permits, emergency controls, statutory safety records and test safety.
Supporting roles
Security Lead; Operations Manager; Fire and Life Safety Consultant
Evidence required
Emergency and operational access review
Gate or milestone blocked
Site shortlist
Risk if delayed
Incident response or normal operations may be delayed.
SIT-014Approve day-one and full-build power requirementUtility DiligencePower DemandElectrical Lead
CriticalTo be assessed
Show details for SIT-014
Task
Approve day-one and full-build power requirement
Completion criteria
IT, cooling, electrical losses, support loads, diversity and contingency are converted into utility demand by phase.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Electrical Lead
Owns electrical design, protection, utility interfaces, energisation readiness and electrical compliance.
Supporting roles
Mechanical and Cooling Lead; Design Manager
Evidence required
Approved power demand model
Gate or milestone blocked
Utility feasibility request
Risk if delayed
Utility engagement may use understated or inconsistent demand.
SIT-015Obtain written utility feasibilityUtility DiligenceUtility CapacityUtility Liaison Lead
CriticalTo be assessed
Show details for SIT-015
Task
Obtain written utility feasibility
Completion criteria
Utility confirms available capacity, source substation, voltage, connection scope, indicative cost and timeline.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Utility Liaison Lead
Coordinates utility feasibility, sanctioned load, route, commercial terms, inspections and energisation.
Supporting roles
Electrical Lead; Site Selection Lead
Evidence required
Utility feasibility letter or formal response
Gate or milestone blocked
Site shortlist
Risk if delayed
Power may be unavailable or arrive after required go-live.
SIT-016Map power connection route and rights-of-wayUtility DiligencePower RouteUtility Liaison Lead
CriticalTo be assessed
Show details for SIT-016
Task
Map power connection route and rights-of-way
Completion criteria
Proposed feeder/cable route, crossings, third-party permissions, owner scope and land needs are identified.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Utility Liaison Lead
Coordinates utility feasibility, sanctioned load, route, commercial terms, inspections and energisation.
Supporting roles
Electrical Lead; Legal Counsel; Approvals Manager
Evidence required
Power route map and ROW note
Gate or milestone blocked
Power schedule and cost baseline
Risk if delayed
Route permission can be the true critical path.
SIT-017Assess source and route diversityUtility DiligenceResilienceElectrical Lead
CriticalTo be assessed
Show details for SIT-017
Task
Assess source and route diversity
Completion criteria
Proposed feeds are traced to upstream sources and common substations, corridors, switchgear and hazards are identified.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Electrical Lead
Owns electrical design, protection, utility interfaces, energisation readiness and electrical compliance.
Supporting roles
Utility Liaison Lead; Insurance and Risk Lead
Evidence required
Power resilience and common-mode assessment
Gate or milestone blocked
Availability design / site shortlist
Risk if delayed
Nominal dual feeds may share one failure point.
SIT-018Review outage and power quality historyUtility DiligenceReliabilityElectrical Lead
HighTo be assessed
Show details for SIT-018
Task
Review outage and power quality history
Completion criteria
Available outage frequency, duration, voltage events and local maintenance constraints are analysed and limitations stated.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Electrical Lead
Owns electrical design, protection, utility interfaces, energisation readiness and electrical compliance.
Supporting roles
Utility Liaison Lead; Operations Manager
Evidence required
Utility reliability review
Gate or milestone blocked
Backup-power design / operating cost
Risk if delayed
Backup runtime and fuel demand may be underestimated.
SIT-019Assess generator, fuel and backup-power logisticsUtility DiligenceBackup PowerElectrical Lead
HighTo be assessed
Show details for SIT-019
Task
Assess generator, fuel and backup-power logistics
Completion criteria
DG yard, emissions/noise, fuel storage, tanker route, replenishment and full-build space are feasible.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Electrical Lead
Owns electrical design, protection, utility interfaces, energisation readiness and electrical compliance.
Supporting roles
Fire and Life Safety Consultant; HSE Manager; Approvals Manager
Evidence required
Backup power site-fit note
Gate or milestone blocked
Concept layout
Risk if delayed
Site constraints may prevent reliable backup power.
SIT-020Confirm future power expansion pathUtility DiligenceExpansionUtility Liaison Lead
CriticalTo be assessed
Show details for SIT-020
Task
Confirm future power expansion path
Completion criteria
Utility and site infrastructure can support later phases with identified upgrades, dates, land and cost.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Utility Liaison Lead
Coordinates utility feasibility, sanctioned load, route, commercial terms, inspections and energisation.
Supporting roles
Electrical Lead; Finance and Commercial Lead
Evidence required
Phased power expansion plan
Gate or milestone blocked
Full-build business case
Risk if delayed
A viable day-one site may become a stranded asset.
SIT-021Compile site-specific climate design conditionsEnvironmental DiligenceClimateMechanical and Cooling Lead
HighTo be assessed
Show details for SIT-021
Task
Compile site-specific climate design conditions
Completion criteria
Peak dry-bulb, wet-bulb, humidity, heat wave, monsoon, dust, air quality and coastal exposure are documented.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Mechanical and Cooling Lead
Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria.
Supporting roles
Water and Environmental Lead; Insurance and Risk Lead
Evidence required
Climate design-condition report
Gate or milestone blocked
Cooling concept screening
Risk if delayed
Catalogue climate assumptions may understate plant size or corrosion.
SIT-022Complete flood, drainage and stormwater assessmentEnvironmental DiligenceFloodCivil and Structural Lead
CriticalTo be assessed
Show details for SIT-022
Task
Complete flood, drainage and stormwater assessment
Completion criteria
Historical events, catchment, site levels, drainage outfall, extreme rainfall and required elevation/mitigation are assessed.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Civil and Structural Lead
Owns civil, structural, drainage, grading, constructability and structural compliance.
Supporting roles
Water and Environmental Lead; Insurance and Risk Lead
Evidence required
Flood and drainage study
Gate or milestone blocked
Site shortlist
Risk if delayed
Flooding can disable access, utilities and critical equipment.
SIT-023Assess seismic and natural-hazard exposureEnvironmental DiligenceSeismic and HazardsCivil and Structural Lead
HighTo be assessed
Show details for SIT-023
Task
Assess seismic and natural-hazard exposure
Completion criteria
Seismic zone, liquefaction where relevant, wind/cyclone, lightning and other location hazards are documented.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Civil and Structural Lead
Owns civil, structural, drainage, grading, constructability and structural compliance.
Supporting roles
Insurance and Risk Lead; HSE Manager
Evidence required
Natural hazards report
Gate or milestone blocked
Structural concept / insurance review
Risk if delayed
Design cost and residual risk may be understated.
SIT-024Estimate day-one and full-build water demandWater DiligenceDemandWater and Environmental Lead
CriticalTo be assessed
Show details for SIT-024
Task
Estimate day-one and full-build water demand
Completion criteria
Cooling, treatment, domestic, fire and process demands are calculated by season and operating mode.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Water and Environmental Lead
Owns water balance, source legality, quality, treatment, discharge and environmental obligations.
Supporting roles
Mechanical and Cooling Lead; Fire and Life Safety Consultant
Evidence required
Approved water demand model
Gate or milestone blocked
Water-source validation
Risk if delayed
Source adequacy cannot be assessed.
SIT-025Validate primary and backup water sourcesWater DiligenceSourceWater and Environmental Lead
CriticalTo be assessed
Show details for SIT-025
Task
Validate primary and backup water sources
Completion criteria
Legal source, permitted quantity, seasonal reliability, agreement terms, backup and expansion capacity are evidenced.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Water and Environmental Lead
Owns water balance, source legality, quality, treatment, discharge and environmental obligations.
Supporting roles
Legal Counsel; Approvals Manager; Finance and Commercial Lead
Evidence required
Water-source feasibility pack
Gate or milestone blocked
Site shortlist
Risk if delayed
Cooling may depend on unavailable or unlawful water.
SIT-026Test source water quality and treatment implicationsWater DiligenceQualityWater and Environmental Lead
HighTo be assessed
Show details for SIT-026
Task
Test source water quality and treatment implications
Completion criteria
Representative tests identify scaling, corrosion, biological and treatment requirements and operating cost impact.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Water and Environmental Lead
Owns water balance, source legality, quality, treatment, discharge and environmental obligations.
Supporting roles
Mechanical and Cooling Lead; Operations Manager
Evidence required
Laboratory report and treatment note
Gate or milestone blocked
Cooling technology selection
Risk if delayed
Poor water quality may damage systems or raise cost.
SIT-027Assess cooling technology fit for climate, water and densityCooling DiligenceTechnology FitMechanical and Cooling Lead
CriticalTo be assessed
Show details for SIT-027
Task
Assess cooling technology fit for climate, water and density
Completion criteria
Viable air, chilled-water, dry, evaporative, hybrid and liquid-cooling options are compared for planned loads.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Mechanical and Cooling Lead
Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria.
Supporting roles
Electrical Lead; Operations Manager; Finance and Commercial Lead
Evidence required
Cooling technology site-fit comparison
Gate or milestone blocked
Site shortlist
Risk if delayed
Selected site may not support required density or sustainability.
SIT-028Validate sewerage, blowdown and wastewater routeEnvironmental DiligenceDischargeWater and Environmental Lead
HighTo be assessed
Show details for SIT-028
Task
Validate sewerage, blowdown and wastewater route
Completion criteria
Discharge path, treatment, quantity, permission and seasonal constraints are confirmed.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Water and Environmental Lead
Owns water balance, source legality, quality, treatment, discharge and environmental obligations.
Supporting roles
Approvals Manager; Legal Counsel
Evidence required
Wastewater and discharge feasibility note
Gate or milestone blocked
Environmental approval path
Risk if delayed
Facility may lack a lawful operating discharge route.
SIT-029Obtain carrier service and capacity confirmationConnectivity DiligenceCarrier AvailabilityTelecom Lead
CriticalTo be assessed
Show details for SIT-029
Task
Obtain carrier service and capacity confirmation
Completion criteria
Required carriers confirm service type, capacity, PoP, commercial lead time and building handoff assumptions.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Telecom Lead
Owns carrier strategy, physical route diversity, right-of-way, building entry and service acceptance.
Supporting roles
IT and Network Lead; Finance and Commercial Lead
Evidence required
Carrier feasibility responses
Gate or milestone blocked
Site shortlist
Risk if delayed
Connectivity may be unavailable or late.
SIT-030Map physical fibre routes and common pointsConnectivity DiligenceRoutesTelecom Lead
CriticalTo be assessed
Show details for SIT-030
Task
Map physical fibre routes and common points
Completion criteria
Routes are traced from PoPs to site, including ducts, bridges, road crossings, chambers and shared infrastructure.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Telecom Lead
Owns carrier strategy, physical route diversity, right-of-way, building entry and service acceptance.
Supporting roles
Legal Counsel; Approvals Manager; IT and Network Lead
Evidence required
Physical fibre route maps
Gate or milestone blocked
Diversity assessment
Risk if delayed
Different carriers may use the same physical path.
SIT-031Validate two physically diverse entrances and pathsConnectivity DiligenceDiversityTelecom Lead
CriticalTo be assessed
Show details for SIT-031
Task
Validate two physically diverse entrances and paths
Completion criteria
Required paths avoid unacceptable common points and can enter separated meet-me rooms or zones.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Telecom Lead
Owns carrier strategy, physical route diversity, right-of-way, building entry and service acceptance.
Supporting roles
Lead Architect; IT and Network Lead; Insurance and Risk Lead
Evidence required
Fibre diversity assessment
Gate or milestone blocked
Connectivity acceptance
Risk if delayed
One excavation or fire event may cut all service.
SIT-032Assess telecom right-of-way, road cutting and delivery scheduleConnectivity DiligenceROW and TimelineApprovals Manager
HighTo be assessed
Show details for SIT-032
Task
Assess telecom right-of-way, road cutting and delivery schedule
Completion criteria
Authority permissions, restoration obligations, route owners and realistic delivery dates are documented.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Approvals Manager
Owns the approval inventory, authority engagement, submissions, conditions, renewals and evidence.
Supporting roles
Telecom Lead; Legal Counsel; PMO Lead
Evidence required
Telecom ROW and schedule note
Gate or milestone blocked
Master schedule
Risk if delayed
Fibre often becomes a late external dependency.
SIT-033Create site-specific approval pathwayRegulatory DiligenceApprovalsApprovals Manager
CriticalTo be assessed
Show details for SIT-033
Task
Create site-specific approval pathway
Completion criteria
Land, building, fire, power, DG/fuel, water, environment, telecom, labour and operating permissions are mapped.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Approvals Manager
Owns the approval inventory, authority engagement, submissions, conditions, renewals and evidence.
Supporting roles
Legal Counsel; Design Manager; PMO Lead
Evidence required
Site approval inventory and timeline
Gate or milestone blocked
Site shortlist
Risk if delayed
Approval complexity may make an otherwise strong site unviable.
SIT-034Assess state policy and incentive eligibilityRegulatory DiligencePolicyFinance and Commercial Lead
MediumTo be assessed
Show details for SIT-034
Task
Assess state policy and incentive eligibility
Completion criteria
Eligibility, deadlines, evidence, benefit timing, continuing obligations and risk-adjusted value are documented.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Finance and Commercial Lead
Owns cost, lifecycle economics, commercial assumptions, incentives and financial validation.
Supporting roles
Approvals Manager; Legal Counsel
Evidence required
Incentive eligibility memorandum
Gate or milestone blocked
Business case
Risk if delayed
Uncertain incentives may be incorrectly treated as committed economics.
SIT-035Assess adjacent industrial, infrastructure and human-made hazardsSecurity DiligenceExternal RiskSecurity Lead
HighTo be assessed
Show details for SIT-035
Task
Assess adjacent industrial, infrastructure and human-made hazards
Completion criteria
Chemical sites, pipelines, HV corridors, transport, airport/defence, vibration, protests and future land use are mapped.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Security Lead
Owns physical security design, access control, CCTV, security procedures and incident escalation.
Supporting roles
HSE Manager; Insurance and Risk Lead; Civil and Structural Lead
Evidence required
External hazard map and risk assessment
Gate or milestone blocked
Site shortlist
Risk if delayed
An external event may disable access or create evacuation risk.
SIT-036Assess perimeter and security design feasibilitySecurity DiligenceSite SecuritySecurity Lead
HighTo be assessed
Show details for SIT-036
Task
Assess perimeter and security design feasibility
Completion criteria
Setbacks, secure perimeter, controlled entries, vehicle screening, critical-area zoning and surveillance are feasible.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Security Lead
Owns physical security design, access control, CCTV, security procedures and incident escalation.
Supporting roles
Lead Architect; Operations Manager; HSE Manager
Evidence required
Site security feasibility review
Gate or milestone blocked
Concept layout
Risk if delayed
Plot constraints may prevent required physical security.
SIT-037Assess operations workforce and vendor ecosystemOperations DiligenceWorkforceOperations Manager
HighTo be assessed
Show details for SIT-037
Task
Assess operations workforce and vendor ecosystem
Completion criteria
Critical skills, shift staffing, transport, OEM support, maintenance vendors, accommodation and emergency support are available.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Operations Manager
Owns operational acceptance, staffing, procedures, monitoring, maintenance and post-handover accountability.
Supporting roles
HR and Training Lead; Procurement Lead; Security Lead
Evidence required
Operations ecosystem assessment
Gate or milestone blocked
Site shortlist
Risk if delayed
Recruitment and support constraints can increase operational risk.
SIT-038Assess fuel, chemicals, spares and consumable logisticsOperations DiligenceSupply ChainOperations Manager
HighTo be assessed
Show details for SIT-038
Task
Assess fuel, chemicals, spares and consumable logistics
Completion criteria
Suppliers, lead times, access, storage, seasonal disruption and alternate sources are documented.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Operations Manager
Owns operational acceptance, staffing, procedures, monitoring, maintenance and post-handover accountability.
Supporting roles
Procurement Lead; HSE Manager; Finance and Commercial Lead
Evidence required
Critical supply-chain assessment
Gate or milestone blocked
Operating model
Risk if delayed
A remote or constrained site may be difficult to sustain.
SIT-039Build comparable site lifecycle cost modelCommercial EvaluationLifecycle CostFinance and Commercial Lead
CriticalTo be assessed
Show details for SIT-039
Task
Build comparable site lifecycle cost model
Completion criteria
Land, civil, utility, ROW, flood, cooling, water, security, taxes, approvals, operations and risk contingencies use common assumptions.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Finance and Commercial Lead
Owns cost, lifecycle economics, commercial assumptions, incentives and financial validation.
Supporting roles
Site Selection Lead; Project Director; Insurance and Risk Lead
Evidence required
Comparable lifecycle cost model
Gate or milestone blocked
Final site scoring
Risk if delayed
Low land price may conceal much higher total cost.
SIT-040Prepare phased site master planExpansion EvaluationMaster PlanningLead Architect
CriticalTo be assessed
Show details for SIT-040
Task
Prepare phased site master plan
Completion criteria
Day-one and full-build buildings, utilities, circulation, security, construction staging and future tie-ins fit without unsafe disruption.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Lead Architect
Owns architectural compliance, building submissions, space planning and authority drawing coordination.
Supporting roles
Civil and Structural Lead; Electrical Lead; Mechanical and Cooling Lead; Operations Manager
Evidence required
Phased master plan
Gate or milestone blocked
Full-build viability
Risk if delayed
Expansion may block operations or require redesign of core infrastructure.
SIT-041Obtain insurance and risk view for shortlisted sitesCommercial EvaluationInsuranceInsurance and Risk Lead
HighTo be assessed
Show details for SIT-041
Task
Obtain insurance and risk view for shortlisted sites
Completion criteria
Insurability, exclusions, required mitigations and indicative premium differences are documented.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Insurance and Risk Lead
Owns hazard/insurability review, risk-transfer requirements and residual-risk advice.
Supporting roles
Finance and Commercial Lead; HSE Manager; Project Director
Evidence required
Insurance risk opinion
Gate or milestone blocked
Final site decision
Risk if delayed
Material hazards may be uninsurable or expensive.
SIT-042Score each candidate with evidence referencesDecisionScorecardSite Selection Lead
CriticalTo be assessed
Show details for SIT-042
Task
Score each candidate with evidence references
Completion criteria
Every criterion has score, rationale, evidence, confidence, owner and open action; unverified items remain N/V.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Site Selection Lead
Owns candidate comparison, evidence pack, scoring, fatal-flaw analysis and recommendation.
Supporting roles
All workstream leads; PMO Lead
Evidence required
Completed evidence-linked site scorecards
Gate or milestone blocked
Final shortlist
Risk if delayed
Optimistic assumptions may be converted into false precision.
SIT-043Perform independent fatal-flaw reviewDecisionFatal FlawsInsurance and Risk Lead
CriticalTo be assessed
Show details for SIT-043
Task
Perform independent fatal-flaw review
Completion criteria
Title, land use, power, hazards, water/cooling, fibre, approvals, access and expansion fatal flaws are closed or site is rejected.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Insurance and Risk Lead
Owns hazard/insurability review, risk-transfer requirements and residual-risk advice.
Supporting roles
Legal Counsel; Electrical Lead; Mechanical and Cooling Lead; Telecom Lead; Approvals Manager
Evidence required
Signed fatal-flaw review
Gate or milestone blocked
Final recommendation
Risk if delayed
A weighted score may conceal an irreversible blocker.
SIT-044Conduct multidisciplinary site verification visitDecisionSite VisitSite Selection Lead
CriticalTo be assessed
Show details for SIT-044
Task
Conduct multidisciplinary site verification visit
Completion criteria
Technical, legal, operations, security and construction representatives verify critical evidence and record discrepancies.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Site Selection Lead
Owns candidate comparison, evidence pack, scoring, fatal-flaw analysis and recommendation.
Supporting roles
Operations Manager; Construction Manager; Security Lead; Electrical Lead; Mechanical and Cooling Lead
Evidence required
Site visit report, photos and action log
Gate or milestone blocked
Final recommendation
Risk if delayed
Desktop evidence may not match physical reality.
SIT-045Prepare site-specific residual risk and mitigation planDecisionRiskInsurance and Risk Lead
CriticalTo be assessed
Show details for SIT-045
Task
Prepare site-specific residual risk and mitigation plan
Completion criteria
Each material risk has cause, impact, mitigation, cost, schedule, owner, trigger and acceptance authority.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Insurance and Risk Lead
Owns hazard/insurability review, risk-transfer requirements and residual-risk advice.
Supporting roles
Site Selection Lead; PMO Lead; Finance and Commercial Lead
Evidence required
Residual risk and mitigation register
Gate or milestone blocked
Investment approval
Risk if delayed
Risks may be accepted without funding or ownership.
SIT-046Prepare site selection decision memorandumDecisionRecommendationSite Selection Lead
CriticalTo be assessed
Show details for SIT-046
Task
Prepare site selection decision memorandum
Completion criteria
Memo compares candidates, explains scoring, fatal flaws, costs, schedule, evidence gaps, residual risks and recommended site.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Site Selection Lead
Owns candidate comparison, evidence pack, scoring, fatal-flaw analysis and recommendation.
Supporting roles
Project Director; Finance and Commercial Lead; Document Controller
Evidence required
Controlled decision memorandum and evidence pack
Gate or milestone blocked
Site approval
Risk if delayed
Decision may not be auditable or defensible.
SIT-047Approve preferred site and transaction conditionsDecisionApprovalExecutive Sponsor
CriticalTo be assessed
Show details for SIT-047
Task
Approve preferred site and transaction conditions
Completion criteria
Decision authority approves site, maximum commercial exposure, conditions precedent, diligence closures and residual risks.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Executive Sponsor
Owns the business decision, funding authority, formal risk acceptance and final escalation.
Supporting roles
Project Director; Legal Counsel; Finance and Commercial Lead
Evidence required
Signed site approval and condition list
Gate or milestone blocked
Land commitment
Risk if delayed
Organisation may commit before critical protections are in place.
SIT-048Close conditions before irrevocable commitmentTransactionConditions PrecedentLegal Counsel
CriticalTo be assessed
Show details for SIT-048
Task
Close conditions before irrevocable commitment
Completion criteria
Legal cures, utility evidence, rights, approvals, surveys, commercial protections and other approved conditions are satisfied or waived by authority.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Legal Counsel
Validates title, contracts, statutory interpretation, legal exposure and formal legal conclusions.
Supporting roles
Site Selection Lead; Project Director; Finance and Commercial Lead
Evidence required
Condition-precedent closure certificate
Gate or milestone blocked
Transaction close
Risk if delayed
Irreversible spend may occur while fatal dependencies remain.
SIT-049Transfer approved site assumptions into design and project controlsClose-outBaselineProject Director
CriticalTo be assessed
Show details for SIT-049
Task
Transfer approved site assumptions into design and project controls
Completion criteria
All site constraints, utility commitments, hazards, mitigations, approvals and expansion assumptions are baselined with owners.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Project Director
Owns end-to-end delivery, cross-workstream decisions, executive escalation and stage-gate readiness.
Supporting roles
Design Manager; PMO Lead; Approvals Manager; Operations Manager
Evidence required
Site handover pack and updated project baselines
Gate or milestone blocked
Concept design mobilisation
Risk if delayed
Site diligence may be forgotten during design and delivery.
This checklist is a project-management framework, not legal, regulatory, engineering or certification advice. Exact requirements vary by location, authority, facility design, operating model and project objectives. Validate applicability with qualified local professionals and the relevant authorities. Completing the checklist does not guarantee approval, certification, uptime or regulatory compliance.