Data Center Project Management

Data Center Project Lifecycle and Stage-Gate Checklist — India

Initiation through feasibility, site, concept, approvals, detailed design, procurement, construction, commissioning, handover, stabilisation, and close-out stage gates.

Source article: Project Managing a Data Center Setup in India·
Share
57
Total tasks
51
Critical tasks
12
Phases
49
Workstreams
19
Accountable owner roles
This checklist is a project-management framework, not legal, regulatory, engineering or certification advice. Exact requirements vary by location, authority, facility design, operating model and project objectives. Validate applicability with qualified local professionals and the relevant authorities. Completing the checklist does not guarantee approval, certification, uptime or regulatory compliance.

How to use this tracker

Each row is an executable work package. Assign a named individual against the accountable role, enter planned start and end dates, follow the predecessor task IDs, and mark a task complete only when its completion criterion is met and supporting evidence has been reviewed.

The owner column deliberately contains the accountable role, not a person’s name, so the tracker stays reusable across organisations. Add a Named_Ownercolumn — or use the local “Named owner” field on each task below — in your working copy.

Using it in Excel

  1. Import the file as UTF-8.
  2. Convert the imported range into an Excel Table.
  3. Freeze the header row.
  4. Use ISO dates in YYYY-MM-DD format.
  5. Add data-validation lists for Status and Applicability.
  6. Filter Critical tasks and blocked project gates during every project review.
  7. Add a Named_Owner column in the working copy.
  8. Record the accepting authority in Notes for Accepted Risk.
  9. Preserve stable Task IDs when customising the tracker.
  10. Do not mark a task complete until its evidence has been reviewed.

Status legend

Not Started
No work has begun on this task yet.
In Progress
Work is underway but the completion criterion is not yet met.
Complete
The completion criterion has been met and supporting evidence has been reviewed. Do not mark a task Complete only because the activity occurred.
Blocked
The task cannot proceed. Record the blocker in Notes.
Not Applicable
Record the reason and the approving authority in Notes.
Accepted Risk
Record the accepting authority, the interim control and the review date in Notes.

Applicability legend

Required
This task applies to the project as scoped.
Conditional
Applicability depends on site, authority, technology, or scope decisions not yet made.
Not Applicable
Confirmed out of scope for this project — record the reason in Notes.
To be assessed
Applicability has not yet been evaluated for this project.

Priority (Critical, High, Medium, Low) and Applicability are always shown as text, never by colour alone.

The complete tracker — 57 tasks

0 / 57
Complete
0%
Percent complete
51
Critical open
0
Blocked
0
Not Applicable (excluded from %)
0
Accepted Risk (open, not counted complete)
56
Tasks with unmet predecessors
57 of 57
Showing

Percent complete = Complete ÷ (Total − Not Applicable). Not Applicable tasks are removed from the denominator because they are out of scope; Accepted Risk tasks stay in the denominator but are never counted as complete, so accepted risk is always visible rather than hidden inside the percentage.

Download blank CSV

Loading saved progress…

Task IDTaskPhaseWorkstreamOwner roleDepends onStatusPriorityApplicabilityDetails
PLC-001Appoint executive sponsor and project directorInitiationSponsorshipExecutive SponsorCriticalTo be assessed
Show details for PLC-001
Task
Appoint executive sponsor and project director
Completion criteria
Sponsor and project director have written decision rights, funding authority, escalation route and accountability for outcomes.
Dependency explanation
Starting task.
Accountable role
Executive Sponsor
Owns the business decision, funding authority, formal risk acceptance and final escalation.
Supporting roles
Project Director; PMO Lead
Evidence required
Approved project charter and appointments
Gate or milestone blocked
Programme mobilisation
Risk if delayed
No authority to resolve cross-functional issues or approve gates.
PLC-002Define business, service and capacity objectivesInitiationBusiness RequirementsProject Director
CriticalTo be assessed
Show details for PLC-002
Task
Define business, service and capacity objectives
Completion criteria
Use case, market, day-one/full-build capacity, service model, schedule, resilience and financial objectives are documented.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Project Director
Owns end-to-end delivery, cross-workstream decisions, executive escalation and stage-gate readiness.
Supporting roles
Executive Sponsor; Operations Manager; Finance and Commercial Lead
Evidence required
Approved business requirements
Gate or milestone blocked
Feasibility study
Risk if delayed
Technical teams may optimise for incompatible objectives.
PLC-003Establish workstreams, RACI and forumsInitiationGovernancePMO Lead
CriticalTo be assessed
Show details for PLC-003
Task
Establish workstreams, RACI and forums
Completion criteria
Every workstream has accountable owner; weekly delivery, risk and steering forums have defined inputs and decisions.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
PMO Lead
Maintains the integrated plan, dependencies, status, evidence, risks, decisions and governance cadence.
Supporting roles
Project Director; all workstream leads
Evidence required
Approved governance plan and RACI
Gate or milestone blocked
Programme baseline
Risk if delayed
Dependencies and decisions may remain ownerless.
PLC-004Create document repository and control conventionsInitiationControlsDocument Controller
HighTo be assessed
Show details for PLC-004
Task
Create document repository and control conventions
Completion criteria
Controlled repository, naming, review, approval, revision, evidence and retention rules are active.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Document Controller
Owns document numbering, version control, repository completeness, transmittals and retrieval.
Supporting roles
PMO Lead; Design Manager; Quality Manager
Evidence required
Document-control procedure and repository
Gate or milestone blocked
First formal deliverable
Risk if delayed
Teams may execute using obsolete information.
PLC-005Create initial risk, assumption, issue and decision logsInitiationRiskPMO Lead
CriticalTo be assessed
Show details for PLC-005
Task
Create initial risk, assumption, issue and decision logs
Completion criteria
Registers have unique IDs, owner, due date, impact, response, escalation and evidence requirements.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
PMO Lead
Maintains the integrated plan, dependencies, status, evidence, risks, decisions and governance cadence.
Supporting roles
Project Director; Insurance and Risk Lead
Evidence required
Controlled RAID and decision registers
Gate or milestone blocked
Feasibility baseline
Risk if delayed
Critical assumptions may become invisible commitments.
PLC-006Build phased IT load and rack-density modelFeasibilityCapacityDesign Manager
CriticalTo be assessed
Show details for PLC-006
Task
Build phased IT load and rack-density model
Completion criteria
Day-one/full-build load, average/peak density, AI zones, growth and diversity assumptions are approved.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Design Manager
Coordinates multidisciplinary design, interfaces, reviews, change control and design freeze.
Supporting roles
Electrical Lead; Mechanical and Cooling Lead; IT and Network Lead
Evidence required
Approved capacity model
Gate or milestone blocked
Utility and cooling feasibility
Risk if delayed
Infrastructure can be materially undersized or overbuilt.
PLC-007Evaluate build, colocation and hybrid optionsFeasibilityDelivery ModelProject Director
HighTo be assessed
Show details for PLC-007
Task
Evaluate build, colocation and hybrid options
Completion criteria
Options are compared for control, schedule, capex, opex, capacity, compliance, resilience, flexibility and exit risk.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Project Director
Owns end-to-end delivery, cross-workstream decisions, executive escalation and stage-gate readiness.
Supporting roles
Finance and Commercial Lead; Operations Manager; Security Lead
Evidence required
Approved delivery-model decision paper
Gate or milestone blocked
Feasibility gate
Risk if delayed
Organisation may build when colocation is better or accept unsuitable third-party capacity.
PLC-008Define resilience and certification objectivesFeasibilityAvailabilityDesign Manager
CriticalTo be assessed
Show details for PLC-008
Task
Define resilience and certification objectives
Completion criteria
Target availability, redundancy, maintainability, failure domains and any certification scope are explicitly defined.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Design Manager
Coordinates multidisciplinary design, interfaces, reviews, change control and design freeze.
Supporting roles
Operations Manager; Insurance and Risk Lead; Compliance Manager
Evidence required
Approved resilience requirements
Gate or milestone blocked
Concept design
Risk if delayed
Labels such as Tier may substitute for actual operating requirements.
PLC-009Estimate power, cooling and water requirementsFeasibilityUtilitiesDesign Manager
CriticalTo be assessed
Show details for PLC-009
Task
Estimate power, cooling and water requirements
Completion criteria
Phased facility power, heat rejection, water and backup requirements are calculated from approved capacity assumptions.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Design Manager
Coordinates multidisciplinary design, interfaces, reviews, change control and design freeze.
Supporting roles
Electrical Lead; Mechanical and Cooling Lead; Water and Environmental Lead
Evidence required
Feasibility utility model
Gate or milestone blocked
Location screening
Risk if delayed
Sites and budgets may be assessed against incorrect utility demand.
PLC-010Prepare preliminary integrated schedule and lifecycle costFeasibilitySchedule and CostPMO Lead
CriticalTo be assessed
Show details for PLC-010
Task
Prepare preliminary integrated schedule and lifecycle cost
Completion criteria
Schedule includes site, approvals, utilities, design, long leads, construction, testing and handover; cost includes capex, opex and contingency.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
PMO Lead
Maintains the integrated plan, dependencies, status, evidence, risks, decisions and governance cadence.
Supporting roles
Finance and Commercial Lead; Procurement Lead; Project Director
Evidence required
Feasibility schedule and cost model
Gate or milestone blocked
Feasibility gate
Risk if delayed
Business case may omit the true critical path or lifecycle expense.
PLC-011Define target operations and support modelFeasibilityOperating ModelOperations Manager
HighTo be assessed
Show details for PLC-011
Task
Define target operations and support model
Completion criteria
Staffing, shifts, outsourcing, maintenance, monitoring, security, compliance, service and incident responsibilities are outlined.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Operations Manager
Owns operational acceptance, staffing, procedures, monitoring, maintenance and post-handover accountability.
Supporting roles
Facilities Manager; Security Lead; HR and Training Lead
Evidence required
Operating model outline
Gate or milestone blocked
Feasibility gate
Risk if delayed
Design may be difficult or expensive to operate.
PLC-012Approve feasibility and funding envelopeFeasibilityStage GateExecutive Sponsor
CriticalTo be assessed
Show details for PLC-012
Task
Approve feasibility and funding envelope
Completion criteria
Sponsor accepts delivery model, requirements, assumptions, risks, preliminary cost/schedule and authorises site diligence.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Executive Sponsor
Owns the business decision, funding authority, formal risk acceptance and final escalation.
Supporting roles
Project Director; Finance and Commercial Lead; PMO Lead
Evidence required
Signed feasibility gate approval
Gate or milestone blocked
Site selection
Risk if delayed
Project may proceed without a coherent business or technical case.
PLC-013Approve site scorecard and fatal-flaw criteriaSite SelectionCriteriaSite Selection Lead
CriticalTo be assessed
Show details for PLC-013
Task
Approve site scorecard and fatal-flaw criteria
Completion criteria
Power, land, hazards, fibre, water, approvals, security, operations, expansion and economics criteria are weighted and approved.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Site Selection Lead
Owns candidate comparison, evidence pack, scoring, fatal-flaw analysis and recommendation.
Supporting roles
Project Director; Insurance and Risk Lead; Operations Manager
Evidence required
Approved site scorecard
Gate or milestone blocked
Site longlist screening
Risk if delayed
Selection may be biased toward land price or incentives.
PLC-014Complete multidisciplinary site diligenceSite SelectionDiligenceSite Selection Lead
CriticalTo be assessed
Show details for PLC-014
Task
Complete multidisciplinary site diligence
Completion criteria
Legal, utility, water, fibre, climate, geotechnical, access, approvals, security, operations and commercial evidence is complete.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Site Selection Lead
Owns candidate comparison, evidence pack, scoring, fatal-flaw analysis and recommendation.
Supporting roles
All technical workstream leads; Legal Counsel; Finance and Commercial Lead
Evidence required
Evidence-linked candidate scorecards
Gate or milestone blocked
Site approval
Risk if delayed
Fatal constraints may appear only after commitment.
PLC-015Approve preferred site and conditions precedentSite SelectionDecisionExecutive Sponsor
CriticalTo be assessed
Show details for PLC-015
Task
Approve preferred site and conditions precedent
Completion criteria
Sponsor approves decision memorandum, residual risks, commercial limits and mandatory pre-commitment conditions.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Executive Sponsor
Owns the business decision, funding authority, formal risk acceptance and final escalation.
Supporting roles
Project Director; Legal Counsel; Finance and Commercial Lead
Evidence required
Signed site approval and condition register
Gate or milestone blocked
Land transaction
Risk if delayed
Organisation may commit to an unviable site.
PLC-016Close site conditions and transfer assumptionsSite SelectionTransactionLegal Counsel
CriticalTo be assessed
Show details for PLC-016
Task
Close site conditions and transfer assumptions
Completion criteria
Required legal, utility, survey, access and risk conditions close; constraints and commitments are transferred into project baselines.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Legal Counsel
Validates title, contracts, statutory interpretation, legal exposure and formal legal conclusions.
Supporting roles
Site Selection Lead; Project Director; PMO Lead
Evidence required
Transaction closure and site handover pack
Gate or milestone blocked
Concept design
Risk if delayed
Diligence conclusions may be lost after transaction.
PLC-017Create and approve basis of designConcept DesignBasis of DesignDesign Manager
CriticalTo be assessed
Show details for PLC-017
Task
Create and approve basis of design
Completion criteria
Capacity, environmental, electrical, cooling, water, telecom, fire, security, monitoring, maintainability and expansion criteria are aligned.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Design Manager
Coordinates multidisciplinary design, interfaces, reviews, change control and design freeze.
Supporting roles
All design leads; Operations Manager
Evidence required
Approved basis of design
Gate or milestone blocked
Concept design freeze
Risk if delayed
Disciplines may design to different assumptions.
PLC-018Develop coordinated concept architectureConcept DesignArchitectureLead Architect
CriticalTo be assessed
Show details for PLC-018
Task
Develop coordinated concept architecture
Completion criteria
Site layout, building zones, electrical topology, cooling concept, utility yards, telecom, fire, security and phasing are coordinated.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Lead Architect
Owns architectural compliance, building submissions, space planning and authority drawing coordination.
Supporting roles
Design Manager; Electrical Lead; Mechanical and Cooling Lead; Civil and Structural Lead
Evidence required
Approved concept design package
Gate or milestone blocked
Approval submissions and cost plan
Risk if delayed
Major interfaces may be discovered during construction.
PLC-019Review concept for operability and maintainabilityConcept DesignOperations ReviewOperations Manager
CriticalTo be assessed
Show details for PLC-019
Task
Review concept for operability and maintainability
Completion criteria
Access, isolation, replacement routes, staffing, monitoring, procedures, spares and concurrent maintenance are assessed.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Operations Manager
Owns operational acceptance, staffing, procedures, monitoring, maintenance and post-handover accountability.
Supporting roles
Facilities Manager; Design Manager; HSE Manager
Evidence required
Operations design-review report and closed actions
Gate or milestone blocked
Concept gate
Risk if delayed
Facility may meet capacity but be unsafe or impractical to operate.
PLC-020Approve concept design and updated business caseConcept DesignStage GateProject Director
CriticalTo be assessed
Show details for PLC-020
Task
Approve concept design and updated business case
Completion criteria
Concept meets requirements; key interfaces, cost, schedule, approvals, risks and operating implications are accepted.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Project Director
Owns end-to-end delivery, cross-workstream decisions, executive escalation and stage-gate readiness.
Supporting roles
Executive Sponsor; Finance and Commercial Lead; PMO Lead
Evidence required
Signed concept gate approval
Gate or milestone blocked
Detailed design and major procurement
Risk if delayed
Project may lock in the wrong architecture.
PLC-021Create integrated approval inventory and scheduleApprovalsStrategyApprovals Manager
CriticalTo be assessed
Show details for PLC-021
Task
Create integrated approval inventory and schedule
Completion criteria
Land, building, fire, power, electrical, DG/fuel, water, environment, telecom, labour and operating approvals have owners and dependencies.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Approvals Manager
Owns the approval inventory, authority engagement, submissions, conditions, renewals and evidence.
Supporting roles
Legal Counsel; PMO Lead; all technical leads
Evidence required
Approved approvals tracker
Gate or milestone blocked
Construction and energisation
Risk if delayed
External approvals can silently become the critical path.
PLC-022Prepare and submit priority approvalsApprovalsSubmissionsApprovals Manager
CriticalTo be assessed
Show details for PLC-022
Task
Prepare and submit priority approvals
Completion criteria
Required concept-stage and long-lead submissions are complete, acknowledged and tracked through authority comments.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Approvals Manager
Owns the approval inventory, authority engagement, submissions, conditions, renewals and evidence.
Supporting roles
Design Manager; Legal Counsel; Document Controller
Evidence required
Submission packages and acknowledgements
Gate or milestone blocked
Detailed design / construction start
Risk if delayed
Late or inconsistent submissions can block milestones.
PLC-023Incorporate authority conditions into design and controlsApprovalsConditionsApprovals Manager
CriticalTo be assessed
Show details for PLC-023
Task
Incorporate authority conditions into design and controls
Completion criteria
Every observation or approval condition is assigned, reflected in design/procurement/construction and evidence-tracked.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Approvals Manager
Owns the approval inventory, authority engagement, submissions, conditions, renewals and evidence.
Supporting roles
Design Manager; PMO Lead; Compliance Manager
Evidence required
Condition closure register
Gate or milestone blocked
Design freeze and operational acceptance
Risk if delayed
Granted approvals may still carry unimplemented conditions.
PLC-024Approve multidisciplinary design schedule and deliverable registerDetailed DesignPlanningDesign Manager
CriticalTo be assessed
Show details for PLC-024
Task
Approve multidisciplinary design schedule and deliverable register
Completion criteria
Design packages, inputs, reviews, interfaces, approval dates, procurement releases and IFC milestones are baselined.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Design Manager
Coordinates multidisciplinary design, interfaces, reviews, change control and design freeze.
Supporting roles
PMO Lead; Procurement Lead; Document Controller
Evidence required
Baselined design schedule and deliverable register
Gate or milestone blocked
Detailed design execution
Risk if delayed
Late inputs can delay procurement or create rework.
PLC-025Complete coordinated electrical designDetailed DesignElectricalElectrical Lead
CriticalTo be assessed
Show details for PLC-025
Task
Complete coordinated electrical design
Completion criteria
Utility, transformers, switchgear, generators, UPS, batteries, distribution, protection, earthing, metering and controls are complete.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Electrical Lead
Owns electrical design, protection, utility interfaces, energisation readiness and electrical compliance.
Supporting roles
Design Manager; Controls and Monitoring Lead; Fire and Life Safety Consultant
Evidence required
Reviewed electrical design package
Gate or milestone blocked
Electrical procurement and IFC release
Risk if delayed
Power architecture or protection gaps can cause systemic failure.
PLC-026Complete coordinated cooling and water designDetailed DesignMechanicalMechanical and Cooling Lead
CriticalTo be assessed
Show details for PLC-026
Task
Complete coordinated cooling and water design
Completion criteria
Loads, equipment, hydraulics, air distribution, treatment, storage, drainage, leak detection, controls and expansion are complete.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Mechanical and Cooling Lead
Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria.
Supporting roles
Water and Environmental Lead; Controls and Monitoring Lead; Design Manager
Evidence required
Reviewed mechanical design package
Gate or milestone blocked
Mechanical procurement and IFC release
Risk if delayed
Cooling may not support density or maintainability.
PLC-027Complete civil, structural and architectural designDetailed DesignCivil and ArchitecturalLead Architect
CriticalTo be assessed
Show details for PLC-027
Task
Complete civil, structural and architectural design
Completion criteria
Foundations, building, levels, drainage, rooms, access, fire separations, equipment routes, loads and security zones are complete.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Lead Architect
Owns architectural compliance, building submissions, space planning and authority drawing coordination.
Supporting roles
Civil and Structural Lead; Fire and Life Safety Consultant; Security Lead
Evidence required
Reviewed civil and architectural package
Gate or milestone blocked
Civil IFC release
Risk if delayed
Building may constrain critical systems or safe operations.
PLC-028Complete fire, security and telecom designDetailed DesignFire Security TelecomDesign Manager
CriticalTo be assessed
Show details for PLC-028
Task
Complete fire, security and telecom design
Completion criteria
Cause-and-effect, suppression, access, CCTV, fibre routes, meet-me rooms, entrances and system interfaces are coordinated.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Design Manager
Coordinates multidisciplinary design, interfaces, reviews, change control and design freeze.
Supporting roles
Fire and Life Safety Consultant; Security Lead; Telecom Lead; IT and Network Lead
Evidence required
Reviewed fire, security and telecom package
Gate or milestone blocked
Specialist procurement and IFC release
Risk if delayed
Critical life-safety or connectivity interfaces may be missed.
PLC-029Complete BMS, DCIM and EPMS designDetailed DesignMonitoring and ControlsControls and Monitoring Lead
CriticalTo be assessed
Show details for PLC-029
Task
Complete BMS, DCIM and EPMS design
Completion criteria
Architecture, points, protocols, alarms, thresholds, trends, reports, access, resilience, cybersecurity and backups are specified.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Controls and Monitoring Lead
Owns BMS/DCIM/EPMS points, sequences, alarms, integrations, access and reporting.
Supporting roles
IT and Network Lead; Security Lead; Operations Manager
Evidence required
Reviewed controls and monitoring package
Gate or milestone blocked
Controls procurement
Risk if delayed
Facility may be operationally blind or insecure.
PLC-030Complete clash, interface and common-mode failure reviewsDetailed DesignCoordinationDesign Manager
CriticalTo be assessed
Show details for PLC-030
Task
Complete clash, interface and common-mode failure reviews
Completion criteria
Physical clashes, scope gaps, shared paths, isolation, maintainability and cross-system failure risks are resolved.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Design Manager
Coordinates multidisciplinary design, interfaces, reviews, change control and design freeze.
Supporting roles
Construction Manager; Commissioning Authority; Operations Manager
Evidence required
Closed coordination and failure-mode review
Gate or milestone blocked
Design freeze
Risk if delayed
Independent systems may fail together or be impossible to maintain.
PLC-031Embed testing and commissioning requirementsDetailed DesignCommissioningCommissioning Authority
CriticalTo be assessed
Show details for PLC-031
Task
Embed testing and commissioning requirements
Completion criteria
Test points, temporary systems, load banks, isolation, procedures, FAT/SAT/IST, evidence and witness requirements are in design and specifications.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Commissioning Authority
Independently challenges test scope, witnesses critical tests and validates readiness and results.
Supporting roles
Commissioning Manager; Design Manager; Procurement Lead
Evidence required
Commissioning design review and action closure
Gate or milestone blocked
Design freeze / procurement release
Risk if delayed
Required performance may be impossible to prove.
PLC-032Freeze design and approve IFC baselineDetailed DesignStage GateProject Director
CriticalTo be assessed
Show details for PLC-032
Task
Freeze design and approve IFC baseline
Completion criteria
All required packages, approvals, operations reviews, commissioning requirements and deviations are approved and controlled.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Project Director
Owns end-to-end delivery, cross-workstream decisions, executive escalation and stage-gate readiness.
Supporting roles
Design Manager; Operations Manager; Approvals Manager; PMO Lead
Evidence required
Signed design-freeze certificate and IFC index
Gate or milestone blocked
Full procurement and construction
Risk if delayed
Uncontrolled design changes can propagate cost, delay and defects.
PLC-033Approve package and contracting strategyProcurementStrategyProcurement Lead
CriticalTo be assessed
Show details for PLC-033
Task
Approve package and contracting strategy
Completion criteria
Scope boundaries, EPC/multi-package approach, interfaces, risk allocation, owner-supplied items and commercial model are explicit.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Procurement Lead
Owns sourcing, tendering, commercial closure, contractual obligations and supplier escalation.
Supporting roles
Project Director; Design Manager; Legal Counsel; Finance and Commercial Lead
Evidence required
Approved procurement strategy and package map
Gate or milestone blocked
Tender release
Risk if delayed
Gaps and overlaps can create major disputes.
PLC-034Create and baseline long-lead registerProcurementLong LeadsProcurement Lead
CriticalTo be assessed
Show details for PLC-034
Task
Create and baseline long-lead register
Completion criteria
Manufacture, approvals, FAT, shipping, customs, delivery and required-on-site dates are tracked against construction need.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Procurement Lead
Owns sourcing, tendering, commercial closure, contractual obligations and supplier escalation.
Supporting roles
PMO Lead; Design Manager; Construction Manager
Evidence required
Approved long-lead register
Gate or milestone blocked
Purchase release
Risk if delayed
Critical equipment may arrive after rooms are ready.
PLC-035Issue technically complete tender packagesProcurementTenderingProcurement Lead
CriticalTo be assessed
Show details for PLC-035
Task
Issue technically complete tender packages
Completion criteria
Scope, specifications, drawings, interfaces, programme, quality, safety, FAT/SAT, documentation, training, spares and warranty are included.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Procurement Lead
Owns sourcing, tendering, commercial closure, contractual obligations and supplier escalation.
Supporting roles
Design Manager; Quality Manager; Commissioning Manager
Evidence required
Issued tender packages and bid register
Gate or milestone blocked
Bid evaluation
Risk if delayed
Vendors may price an incomplete scope and later claim variations.
PLC-036Complete technical, commercial and delivery evaluationProcurementEvaluationProcurement Lead
CriticalTo be assessed
Show details for PLC-036
Task
Complete technical, commercial and delivery evaluation
Completion criteria
Compliance deviations, interfaces, lifecycle cost, capacity, schedule, support, references and risk are compared on common basis.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Procurement Lead
Owns sourcing, tendering, commercial closure, contractual obligations and supplier escalation.
Supporting roles
Design Manager; Finance and Commercial Lead; Operations Manager; Quality Manager
Evidence required
Approved evaluation and recommendation
Gate or milestone blocked
Contract award
Risk if delayed
Lowest price may conceal non-compliance or schedule risk.
PLC-037Award contracts with complete delivery obligationsProcurementContractingProcurement Lead
CriticalTo be assessed
Show details for PLC-037
Task
Award contracts with complete delivery obligations
Completion criteria
Final scope, interfaces, milestones, testing, evidence, training, spares, warranty, AMC, damages and change control are executed.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Procurement Lead
Owns sourcing, tendering, commercial closure, contractual obligations and supplier escalation.
Supporting roles
Legal Counsel; Project Director; Finance and Commercial Lead
Evidence required
Executed contracts and responsibility matrix
Gate or milestone blocked
Manufacturing / mobilisation
Risk if delayed
Missing obligations become project cost and handover gaps.
PLC-038Track vendor engineering, manufacturing, FAT and logisticsProcurementExpeditingProcurement Lead
CriticalTo be assessed
Show details for PLC-038
Task
Track vendor engineering, manufacturing, FAT and logistics
Completion criteria
Submittals, approvals, materials, production, tests, shipment, customs and delivery are forecast and escalated.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Procurement Lead
Owns sourcing, tendering, commercial closure, contractual obligations and supplier escalation.
Supporting roles
PMO Lead; Quality Manager; Commissioning Manager
Evidence required
Current expediting report and recovery actions
Gate or milestone blocked
Construction and commissioning
Risk if delayed
Vendor slippage may be discovered too late to recover.
PLC-039Approve mobilisation, HSE, quality and logistics plansConstructionMobilisationConstruction Manager
CriticalTo be assessed
Show details for PLC-039
Task
Approve mobilisation, HSE, quality and logistics plans
Completion criteria
Site setup, access, temporary works, permits, inspections, material handling, emergency arrangements and interfaces are approved.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Construction Manager
Owns site execution, sequencing, contractor interfaces, installation readiness and completion.
Supporting roles
HSE Manager; Quality Manager; Security Lead; PMO Lead
Evidence required
Approved mobilisation pack
Gate or milestone blocked
Construction start
Risk if delayed
Unsafe or disorganised mobilisation can cause incidents and delays.
PLC-040Baseline detailed construction and installation scheduleConstructionScheduleConstruction Manager
CriticalTo be assessed
Show details for PLC-040
Task
Baseline detailed construction and installation schedule
Completion criteria
Activities, quantities, interfaces, work fronts, labour, equipment deliveries, inspections, energisation and commissioning releases are linked.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Construction Manager
Owns site execution, sequencing, contractor interfaces, installation readiness and completion.
Supporting roles
PMO Lead; Procurement Lead; Commissioning Manager
Evidence required
Baselined level-3/4 schedule
Gate or milestone blocked
Construction control
Risk if delayed
Reported progress may not reflect true system readiness.
PLC-041Control civil and architectural constructionConstructionExecutionConstruction Manager
CriticalTo be assessed
Show details for PLC-041
Task
Control civil and architectural construction
Completion criteria
Works follow approved drawings, quality plans and hold points; embedded services, levels, fire separations and equipment routes are verified.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Construction Manager
Owns site execution, sequencing, contractor interfaces, installation readiness and completion.
Supporting roles
Civil and Structural Lead; Lead Architect; Quality Manager
Evidence required
Inspection records and accepted progress
Gate or milestone blocked
MEP installation
Risk if delayed
Civil defects can constrain all downstream systems.
PLC-042Control electrical and mechanical installationConstructionExecutionConstruction Manager
CriticalTo be assessed
Show details for PLC-042
Task
Control electrical and mechanical installation
Completion criteria
Equipment, cables, busduct, pipework, controls, supports, labels, earthing, cleanliness and access follow approved design.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Construction Manager
Owns site execution, sequencing, contractor interfaces, installation readiness and completion.
Supporting roles
Electrical Lead; Mechanical and Cooling Lead; Quality Manager
Evidence required
Installation inspection and test records
Gate or milestone blocked
Pre-commissioning
Risk if delayed
Installation defects can surface under live load.
PLC-043Run interface, RFI and field-change controlConstructionInterfacesDesign Manager
CriticalTo be assessed
Show details for PLC-043
Task
Run interface, RFI and field-change control
Completion criteria
Queries and changes have technical, safety, approval, cost, schedule, redundancy, commissioning and operations impact review before work.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Design Manager
Coordinates multidisciplinary design, interfaces, reviews, change control and design freeze.
Supporting roles
Construction Manager; PMO Lead; Operations Manager; Commissioning Manager
Evidence required
Current RFI/change registers and approved dispositions
Gate or milestone blocked
Affected construction work
Risk if delayed
Informal field changes can undermine resilience and approvals.
PLC-044Manage defects, inspections and progressive as-builtsConstructionQualityQuality Manager
CriticalTo be assessed
Show details for PLC-044
Task
Manage defects, inspections and progressive as-builts
Completion criteria
Non-conformances, snags and inspections are evidence-controlled; as-built changes and asset data are captured during work.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Quality Manager
Owns inspection plans, quality records, non-conformance, snag closure and evidence quality.
Supporting roles
Construction Manager; Document Controller; Design Manager
Evidence required
Quality dashboard, snag register and progressive as-builts
Gate or milestone blocked
System completion
Risk if delayed
Late documentation and hidden defects delay testing and handover.
PLC-045Approve mechanical and electrical completionConstructionStage GateProject Director
CriticalTo be assessed
Show details for PLC-045
Task
Approve mechanical and electrical completion
Completion criteria
Required construction, inspections, labels, safety, documents, utilities and allowable open items satisfy system release criteria.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Project Director
Owns end-to-end delivery, cross-workstream decisions, executive escalation and stage-gate readiness.
Supporting roles
Construction Manager; Quality Manager; Commissioning Manager; HSE Manager
Evidence required
Signed completion and test-release certificates
Gate or milestone blocked
Commissioning
Risk if delayed
Premature energisation or testing can damage equipment or injure people.
PLC-046Approve commissioning plan, schedule and safety controlsCommissioningPlanningCommissioning Manager
CriticalTo be assessed
Show details for PLC-046
Task
Approve commissioning plan, schedule and safety controls
Completion criteria
Systems, levels, procedures, witnesses, resources, permits, defects, evidence, load banks and IST are baselined.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Commissioning Manager
Owns commissioning strategy, test plans, witnesses, execution, defects, retests and evidence.
Supporting roles
Commissioning Authority; HSE Manager; Operations Manager
Evidence required
Approved commissioning plan
Gate or milestone blocked
Functional testing
Risk if delayed
Testing may be incomplete, unsafe or disputed.
PLC-047Complete pre-functional and functional testingCommissioningExecutionCommissioning Manager
CriticalTo be assessed
Show details for PLC-047
Task
Complete pre-functional and functional testing
Completion criteria
All systems pass approved installation, electrical, mechanical, controls, fire, telecom and security tests with evidence.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Commissioning Manager
Owns commissioning strategy, test plans, witnesses, execution, defects, retests and evidence.
Supporting roles
All technical leads; Quality Manager; Operations Manager
Evidence required
Signed system test dossiers
Gate or milestone blocked
Integrated testing
Risk if delayed
Individual systems may not perform as designed.
PLC-048Complete load-bank and failure-scenario testingCommissioningIntegrated TestingCommissioning Authority
CriticalTo be assessed
Show details for PLC-048
Task
Complete load-bank and failure-scenario testing
Completion criteria
Realistic load and approved failures prove power, cooling, monitoring, fire, telecom and operator response and recovery.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Commissioning Authority
Independently challenges test scope, witnesses critical tests and validates readiness and results.
Supporting roles
Commissioning Manager; Operations Manager; HSE Manager
Evidence required
Signed load-bank and IST reports
Gate or milestone blocked
Commissioning acceptance
Risk if delayed
End-to-end resilience remains theoretical.
PLC-049Close commissioning defects and residual-risk reviewCommissioningDefectsQuality Manager
CriticalTo be assessed
Show details for PLC-049
Task
Close commissioning defects and residual-risk review
Completion criteria
Critical defects close; affected tests repeat; remaining items have controls, owners, dates and authorised acceptance.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Quality Manager
Owns inspection plans, quality records, non-conformance, snag closure and evidence quality.
Supporting roles
Commissioning Manager; Project Director; Operations Manager
Evidence required
Final defect and residual-risk register
Gate or milestone blocked
Commissioning acceptance
Risk if delayed
Known weaknesses may transfer to operations.
PLC-050Approve commissioning acceptanceCommissioningStage GateProject Director
CriticalTo be assessed
Show details for PLC-050
Task
Approve commissioning acceptance
Completion criteria
Required tests pass, evidence is complete, operations witnessed results and residual risks are approved.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Project Director
Owns end-to-end delivery, cross-workstream decisions, executive escalation and stage-gate readiness.
Supporting roles
Commissioning Authority; Operations Manager; Executive Sponsor
Evidence required
Signed commissioning acceptance
Gate or milestone blocked
Operations handover
Risk if delayed
Unproven systems may be declared complete.
PLC-051Complete documents, asset and configuration handoverHandoverDocuments and AssetsDocument Controller
CriticalTo be assessed
Show details for PLC-051
Task
Complete documents, asset and configuration handover
Completion criteria
As-builts, manuals, commissioning, approvals, asset register, configurations, credentials, warranties and repository access are accepted.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Document Controller
Owns document numbering, version control, repository completeness, transmittals and retrieval.
Supporting roles
Operations Manager; Design Manager; Procurement Lead; Compliance Manager
Evidence required
Signed document and asset acceptance register
Gate or milestone blocked
Operations acceptance
Risk if delayed
Operations may inherit systems without reliable information.
PLC-052Complete staffing, procedures, training and drillsHandoverPeople and ProceduresOperations Manager
CriticalTo be assessed
Show details for PLC-052
Task
Complete staffing, procedures, training and drills
Completion criteria
Required roles and rosters are active; SOPs/MOPs/EOPs are validated; competence and incident response are demonstrated.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Operations Manager
Owns operational acceptance, staffing, procedures, monitoring, maintenance and post-handover accountability.
Supporting roles
HR and Training Lead; HSE Manager; Commissioning Manager
Evidence required
Staffing, procedure, training and drill evidence
Gate or milestone blocked
Operational go-live
Risk if delayed
Technically complete facility may still be operationally unsafe.
PLC-053Activate maintenance, spares, security and compliance controlsHandoverSupport and ComplianceOperations Manager
CriticalTo be assessed
Show details for PLC-053
Task
Activate maintenance, spares, security and compliance controls
Completion criteria
AMCs, warranties, spares, vendor escalations, access reviews, renewal calendar and operational evidence retention are active.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Operations Manager
Owns operational acceptance, staffing, procedures, monitoring, maintenance and post-handover accountability.
Supporting roles
Facilities Manager; Security Lead; Compliance Manager; Procurement Lead
Evidence required
Operations support readiness pack
Gate or milestone blocked
Operational go-live
Risk if delayed
Failures or renewals may have no support or owner.
PLC-054Sign operations responsibility transferHandoverFinal GateExecutive Sponsor
CriticalTo be assessed
Show details for PLC-054
Task
Sign operations responsibility transfer
Completion criteria
All approved operational acceptance criteria are met and open risks have authorised owners, dates and controls.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Executive Sponsor
Owns the business decision, funding authority, formal risk acceptance and final escalation.
Supporting roles
Project Director; Operations Manager; Compliance Manager
Evidence required
Signed handover certificate
Gate or milestone blocked
Go-live
Risk if delayed
Responsibility may transfer before capability and controls exist.
PLC-055Run stabilisation and close final defectsStabilisationEarly Life SupportOperations Manager
HighTo be assessed
Show details for PLC-055
Task
Run stabilisation and close final defects
Completion criteria
Early alarms, incidents, capacity, defects, vendor support and documentation gaps are reviewed until exit criteria are met.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Operations Manager
Owns operational acceptance, staffing, procedures, monitoring, maintenance and post-handover accountability.
Supporting roles
Project Director; Commissioning Manager; OEM or System Vendor
Evidence required
Stabilisation dashboard and exit approval
Gate or milestone blocked
Project close-out
Risk if delayed
Latent defects can burden operations after project team demobilises.
PLC-056Close contracts, claims and final accountsClose-outCommercialFinance and Commercial Lead
HighTo be assessed
Show details for PLC-056
Task
Close contracts, claims and final accounts
Completion criteria
Deliverables, defects, warranties, retention, claims, variations and final payments are reconciled without releasing unresolved obligations.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Finance and Commercial Lead
Owns cost, lifecycle economics, commercial assumptions, incentives and financial validation.
Supporting roles
Procurement Lead; Legal Counsel; Project Director
Evidence required
Approved commercial close-out statement
Gate or milestone blocked
Programme closure
Risk if delayed
Organisation may lose leverage over vendors.
PLC-057Complete programme close-out and lessons learnedClose-outLessons LearnedPMO Lead
MediumTo be assessed
Show details for PLC-057
Task
Complete programme close-out and lessons learned
Completion criteria
Final scope, cost, schedule, benefits, risks, decisions and lessons are recorded; reusable standards and actions are assigned.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
PMO Lead
Maintains the integrated plan, dependencies, status, evidence, risks, decisions and governance cadence.
Supporting roles
Project Director; Operations Manager; all workstream leads
Evidence required
Approved close-out and lessons-learned report
Gate or milestone blocked
Programme closure
Risk if delayed
Future phases repeat avoidable design and delivery failures.
This checklist is a project-management framework, not legal, regulatory, engineering or certification advice. Exact requirements vary by location, authority, facility design, operating model and project objectives. Validate applicability with qualified local professionals and the relevant authorities. Completing the checklist does not guarantee approval, certification, uptime or regulatory compliance.