Data Center Cooling and Water Planning Checklist — India
Load and climate basis, water source and quality, technology selection, detailed design, procurement, installation, testing, and operations for cooling and water planning.
How to use this tracker
Each row is an executable work package. Assign a named individual against the accountable role, enter planned start and end dates, follow the predecessor task IDs, and mark a task complete only when its completion criterion is met and supporting evidence has been reviewed.
The owner column deliberately contains the accountable role, not a person’s name, so the tracker stays reusable across organisations. Add a Named_Ownercolumn — or use the local “Named owner” field on each task below — in your working copy.
Using it in Excel
- Import the file as UTF-8.
- Convert the imported range into an Excel Table.
- Freeze the header row.
- Use ISO dates in YYYY-MM-DD format.
- Add data-validation lists for Status and Applicability.
- Filter Critical tasks and blocked project gates during every project review.
- Add a Named_Owner column in the working copy.
- Record the accepting authority in Notes for Accepted Risk.
- Preserve stable Task IDs when customising the tracker.
- Do not mark a task complete until its evidence has been reviewed.
Status legend
- Not Started
- No work has begun on this task yet.
- In Progress
- Work is underway but the completion criterion is not yet met.
- Complete
- The completion criterion has been met and supporting evidence has been reviewed. Do not mark a task Complete only because the activity occurred.
- Blocked
- The task cannot proceed. Record the blocker in Notes.
- Not Applicable
- Record the reason and the approving authority in Notes.
- Accepted Risk
- Record the accepting authority, the interim control and the review date in Notes.
Applicability legend
- Required
- This task applies to the project as scoped.
- Conditional
- Applicability depends on site, authority, technology, or scope decisions not yet made.
- Not Applicable
- Confirmed out of scope for this project — record the reason in Notes.
- To be assessed
- Applicability has not yet been evaluated for this project.
Priority (Critical, High, Medium, Low) and Applicability are always shown as text, never by colour alone.
The complete tracker — 55 tasks
Percent complete = Complete ÷ (Total − Not Applicable). Not Applicable tasks are removed from the denominator because they are out of scope; Accepted Risk tasks stay in the denominator but are never counted as complete, so accepted risk is always visible rather than hidden inside the percentage.
Loading saved progress…
| Task ID | Task | Phase | Workstream | Owner role | Depends on | Status | Priority | Applicability | Details |
|---|---|---|---|---|---|---|---|---|---|
| CLW-001 | Appoint cooling and water workstream owner | Initiation | Governance | Mechanical and Cooling Lead | — | Critical | To be assessed | ||
Show details for CLW-001Hide details for CLW-001Task Appoint cooling and water workstream owner Completion criteria Named owner controls requirements, option evaluation, design interfaces, water evidence, approvals, testing and operations readiness. Dependency explanation Starting task. Accountable role Mechanical and Cooling Lead Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria. Supporting roles Project Director; Water and Environmental Lead; PMO Lead Evidence required Approved appointment and RACI Gate or milestone blocked Cooling and water mobilisation Risk if delayed Power, cooling, water and site decisions may diverge. | |||||||||
| CLW-002 | Approve phased IT heat-load and density model | Requirements | IT Load | Design Manager | Critical | To be assessed | |||
Show details for CLW-002Hide details for CLW-002Task Approve phased IT heat-load and density model Completion criteria Day-one/full-build load, diversity, average/peak rack density, AI zones and growth assumptions are approved. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Design Manager Coordinates multidisciplinary design, interfaces, reviews, change control and design freeze. Supporting roles Mechanical and Cooling Lead; Electrical Lead; IT and Network Lead Evidence required Approved IT load and density model Gate or milestone blocked Cooling feasibility Risk if delayed Plant and distribution may be incorrectly sized. | |||||||||
| CLW-003 | Define operating environmental and resilience requirements | Requirements | Environmental Envelope | Mechanical and Cooling Lead | Critical | To be assessed | |||
Show details for CLW-003Hide details for CLW-003Task Define operating environmental and resilience requirements Completion criteria Temperature, humidity, allowable excursions, redundancy, maintainability, recovery and monitoring requirements are approved. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Mechanical and Cooling Lead Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria. Supporting roles Operations Manager; Design Manager; Insurance and Risk Lead Evidence required Approved environmental design criteria Gate or milestone blocked Cooling concept Risk if delayed Different teams may use inconsistent performance criteria. | |||||||||
| CLW-004 | Compile site-specific climate design data | Site Inputs | Climate | Mechanical and Cooling Lead | Critical | To be assessed | |||
Show details for CLW-004Hide details for CLW-004Task Compile site-specific climate design data Completion criteria Peak dry-bulb, wet-bulb, humidity, heat wave, monsoon, dust, air quality and corrosion conditions are documented. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Mechanical and Cooling Lead Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria. Supporting roles Water and Environmental Lead; Insurance and Risk Lead Evidence required Climate design-condition report Gate or milestone blocked Technology screening Risk if delayed Favourable averages may conceal peak-condition failure. | |||||||||
| CLW-005 | Document site, space and utility constraints | Site Inputs | Constraints | Lead Architect | High | To be assessed | |||
Show details for CLW-005Hide details for CLW-005Task Document site, space and utility constraints Completion criteria Available plant space, roofs/yards, heights, loads, acoustic limits, electrical capacity, access, phasing and replacement routes are known. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Lead Architect Owns architectural compliance, building submissions, space planning and authority drawing coordination. Supporting roles Mechanical and Cooling Lead; Electrical Lead; Civil and Structural Lead; Operations Manager Evidence required Site constraint and interface register Gate or milestone blocked Cooling concept Risk if delayed Selected technology may not physically fit or be maintainable. | |||||||||
| CLW-006 | Calculate day-one and full-build water demand | Water Feasibility | Demand | Water and Environmental Lead | Critical | To be assessed | |||
Show details for CLW-006Hide details for CLW-006Task Calculate day-one and full-build water demand Completion criteria Cooling make-up, blowdown, treatment, domestic, fire and contingency demands are calculated by season and operating mode. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Water and Environmental Lead Owns water balance, source legality, quality, treatment, discharge and environmental obligations. Supporting roles Mechanical and Cooling Lead; Fire and Life Safety Consultant Evidence required Approved water balance Gate or milestone blocked Water-source diligence Risk if delayed Source adequacy and permissions cannot be evaluated. | |||||||||
| CLW-007 | Identify primary, secondary and emergency water sources | Water Feasibility | Source | Water and Environmental Lead | Critical | To be assessed | |||
Show details for CLW-007Hide details for CLW-007Task Identify primary, secondary and emergency water sources Completion criteria Every proposed source has location, provider, legal basis, quantity, seasonality, delivery method and expansion potential. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Water and Environmental Lead Owns water balance, source legality, quality, treatment, discharge and environmental obligations. Supporting roles Legal Counsel; Approvals Manager; Finance and Commercial Lead Evidence required Water-source register Gate or milestone blocked Source validation Risk if delayed Project may rely on one undocumented or fragile source. | |||||||||
| CLW-008 | Validate legal right, allocation and approval path | Water Feasibility | Legal and Approvals | Approvals Manager | Critical | To be assessed | |||
Show details for CLW-008Hide details for CLW-008Task Validate legal right, allocation and approval path Completion criteria Supply agreements, permitted quantity, groundwater applicability, authority approvals and continuing conditions are confirmed. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Approvals Manager Owns the approval inventory, authority engagement, submissions, conditions, renewals and evidence. Supporting roles Water and Environmental Lead; Legal Counsel; Compliance Manager Evidence required Legal and approval feasibility memorandum Gate or milestone blocked Technology selection / site commitment Risk if delayed Cooling may depend on unlawful abstraction or uncertain supply. | |||||||||
| CLW-009 | Assess seasonal availability and drought risk | Water Feasibility | Reliability | Water and Environmental Lead | Critical | To be assessed | |||
Show details for CLW-009Hide details for CLW-009Task Assess seasonal availability and drought risk Completion criteria Historical restrictions, competing demand, drought periods, provider outages and climate trends are reflected in source reliability. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Water and Environmental Lead Owns water balance, source legality, quality, treatment, discharge and environmental obligations. Supporting roles Insurance and Risk Lead; Operations Manager Evidence required Seasonal water reliability assessment Gate or milestone blocked Water resilience design Risk if delayed Annual supply volume can hide critical summer shortages. | |||||||||
| CLW-010 | Complete representative source-water testing | Water Feasibility | Quality | Water and Environmental Lead | High | To be assessed | |||
Show details for CLW-010Hide details for CLW-010Task Complete representative source-water testing Completion criteria Tests cover hardness, conductivity, chlorides, silica, pH, suspended solids, biological and other treatment-relevant parameters. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Water and Environmental Lead Owns water balance, source legality, quality, treatment, discharge and environmental obligations. Supporting roles Mechanical and Cooling Lead; Quality Manager Evidence required Accredited laboratory reports Gate or milestone blocked Treatment design Risk if delayed Scaling, corrosion or fouling may be underestimated. | |||||||||
| CLW-011 | Define water-treatment and chemistry requirements | Water Feasibility | Treatment | Water and Environmental Lead | Critical | To be assessed | |||
Show details for CLW-011Hide details for CLW-011Task Define water-treatment and chemistry requirements Completion criteria Filtration, softening, dosing, cycles of concentration, biological control, monitoring and consumables are defined from test results. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Water and Environmental Lead Owns water balance, source legality, quality, treatment, discharge and environmental obligations. Supporting roles Mechanical and Cooling Lead; Operations Manager; OEM or System Vendor Evidence required Water treatment basis and chemistry limits Gate or milestone blocked Technology and equipment selection Risk if delayed Incorrect chemistry can damage plant and increase water use. | |||||||||
| CLW-012 | Define storage and emergency replenishment strategy | Water Feasibility | Storage and Backup | Water and Environmental Lead | Critical | To be assessed | |||
Show details for CLW-012Hide details for CLW-012Task Define storage and emergency replenishment strategy Completion criteria Required autonomy, storage volumes, segregation, refill rates, tanker logistics, connection points and emergency contracts are documented. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Water and Environmental Lead Owns water balance, source legality, quality, treatment, discharge and environmental obligations. Supporting roles Lead Architect; Operations Manager; Security Lead Evidence required Approved storage and backup strategy Gate or milestone blocked Site layout and water resilience Risk if delayed Cooling may fail before emergency water arrives. | |||||||||
| CLW-013 | Validate blowdown, wastewater and drainage route | Water Feasibility | Discharge | Water and Environmental Lead | Critical | To be assessed | |||
Show details for CLW-013Hide details for CLW-013Task Validate blowdown, wastewater and drainage route Completion criteria Quantities, quality, treatment, sewer/discharge path, permissions, sampling and seasonal constraints are confirmed. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Water and Environmental Lead Owns water balance, source legality, quality, treatment, discharge and environmental obligations. Supporting roles Approvals Manager; Civil and Structural Lead; Legal Counsel Evidence required Discharge feasibility and approval note Gate or milestone blocked Cooling concept / environmental approval Risk if delayed No lawful or practical disposal route may exist. | |||||||||
| CLW-014 | Create cooling technology option set | Concept Selection | Options | Mechanical and Cooling Lead | High | To be assessed | |||
Show details for CLW-014Hide details for CLW-014Task Create cooling technology option set Completion criteria Applicable air, DX, chilled-water, dry, evaporative, hybrid, rear-door, direct-to-chip and immersion options are identified. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Mechanical and Cooling Lead Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria. Supporting roles Design Manager; Operations Manager; OEM or System Vendor Evidence required Cooling technology longlist Gate or milestone blocked Option evaluation Risk if delayed Team may prematurely select a familiar technology. | |||||||||
| CLW-015 | Compare options for technical and site fit | Concept Selection | Evaluation | Mechanical and Cooling Lead | Critical | To be assessed | |||
Show details for CLW-015Hide details for CLW-015Task Compare options for technical and site fit Completion criteria Each option is scored for density, climate, peak performance, water, power, space, redundancy, maintenance, support and expansion. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Mechanical and Cooling Lead Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria. Supporting roles Electrical Lead; Water and Environmental Lead; Operations Manager; Insurance and Risk Lead Evidence required Evidence-linked technology scorecard Gate or milestone blocked Concept selection Risk if delayed A lower-PUE option may create unacceptable water or operational risk. | |||||||||
| CLW-016 | Compare lifecycle energy, water and maintenance cost | Concept Selection | Lifecycle Cost | Finance and Commercial Lead | High | To be assessed | |||
Show details for CLW-016Hide details for CLW-016Task Compare lifecycle energy, water and maintenance cost Completion criteria Capex, peak and part-load energy, water, treatment, chemicals, staffing, service, replacement and risk contingencies use common assumptions. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Finance and Commercial Lead Owns cost, lifecycle economics, commercial assumptions, incentives and financial validation. Supporting roles Mechanical and Cooling Lead; Water and Environmental Lead; Operations Manager Evidence required Lifecycle cost comparison Gate or milestone blocked Concept approval Risk if delayed Low initial cost may produce high operating expense. | |||||||||
| CLW-017 | Set evidence-based PUE and WUE targets | Concept Selection | Sustainability | Mechanical and Cooling Lead | High | To be assessed | |||
Show details for CLW-017Hide details for CLW-017Task Set evidence-based PUE and WUE targets Completion criteria Targets specify boundary, load level, climate basis, measurement points, exclusions and reporting method. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Mechanical and Cooling Lead Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria. Supporting roles Water and Environmental Lead; Controls and Monitoring Lead; Finance and Commercial Lead Evidence required Approved efficiency KPI definition Gate or milestone blocked Concept approval Risk if delayed Marketing targets may be unmeasurable or achieved by shifting resource use. | |||||||||
| CLW-018 | Approve cooling and water concept | Concept Selection | Decision | Project Director | Critical | To be assessed | |||
Show details for CLW-018Hide details for CLW-018Task Approve cooling and water concept Completion criteria Decision authority accepts selected technology, water dependency, power impact, lifecycle cost, resilience, risks and expansion approach. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Project Director Owns end-to-end delivery, cross-workstream decisions, executive escalation and stage-gate readiness. Supporting roles Mechanical and Cooling Lead; Operations Manager; Finance and Commercial Lead Evidence required Signed concept decision memorandum Gate or milestone blocked Detailed design Risk if delayed Major plant architecture may be locked without explicit trade-off acceptance. | |||||||||
| CLW-019 | Complete detailed cooling load and diversity model | Detailed Design | Load Model | Mechanical and Cooling Lead | Critical | To be assessed | |||
Show details for CLW-019Hide details for CLW-019Task Complete detailed cooling load and diversity model Completion criteria IT, UPS, electrical, people, lighting, envelope, infiltration and future loads are calculated by zone and phase. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Mechanical and Cooling Lead Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria. Supporting roles Electrical Lead; Lead Architect; Design Manager Evidence required Reviewed cooling load calculation Gate or milestone blocked Equipment sizing Risk if delayed System may be undersized, oversized or poorly phased. | |||||||||
| CLW-020 | Select primary cooling equipment at site conditions | Detailed Design | Equipment | Mechanical and Cooling Lead | Critical | To be assessed | |||
Show details for CLW-020Hide details for CLW-020Task Select primary cooling equipment at site conditions Completion criteria Capacity, turndown, efficiency, redundancy, ambient derating, sound, materials and maintainability meet approved criteria. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Mechanical and Cooling Lead Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria. Supporting roles OEM or System Vendor; Operations Manager; Electrical Lead Evidence required Approved equipment selection schedules Gate or milestone blocked Procurement release Risk if delayed Catalogue ratings may not apply at local peak conditions. | |||||||||
| CLW-021 | Complete hydraulic design and calculations | Detailed Design | Hydraulics | Mechanical and Cooling Lead | Critical | To be assessed | |||
Show details for CLW-021Hide details for CLW-021Task Complete hydraulic design and calculations Completion criteria Pipe sizes, flows, pressure drops, pump head, expansion, water volume, balancing and transient considerations are approved. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Mechanical and Cooling Lead Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria. Supporting roles Design Manager; OEM or System Vendor Evidence required Reviewed hydraulic calculations and P&IDs Gate or milestone blocked Mechanical IFC release Risk if delayed Poor flow or pressure can defeat cooling capacity. | |||||||||
| CLW-022 | Complete room and rack air-distribution design | Detailed Design | Air Distribution | Mechanical and Cooling Lead | Critical | To be assessed | |||
Show details for CLW-022Hide details for CLW-022Task Complete room and rack air-distribution design Completion criteria Airflow, containment, pressure, return paths, blanking, leakage and high-density zones maintain required rack inlet conditions. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Mechanical and Cooling Lead Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria. Supporting roles Lead Architect; IT and Network Lead; Operations Manager Evidence required CFD/airflow analysis or approved distribution design Gate or milestone blocked White-space IFC release Risk if delayed Plant capacity may not reach the racks that need it. | |||||||||
| CLW-023 | Define high-density liquid-cooling interfaces | Detailed Design | Liquid Cooling | Mechanical and Cooling Lead | Critical | Conditional | |||
Show details for CLW-023Hide details for CLW-023Task Define high-density liquid-cooling interfaces Completion criteria CDUs, facility water interface, pressure, temperature, chemistry, redundancy, leak containment, drains and ownership are defined. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Mechanical and Cooling Lead Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria. Supporting roles IT and Network Lead; OEM or System Vendor; Water and Environmental Lead Evidence required Approved liquid-cooling interface specification Gate or milestone blocked High-density procurement and fit-out Risk if delayed IT and facility systems may have incompatible limits. | |||||||||
| CLW-024 | Design treatment, make-up, storage and discharge systems | Detailed Design | Water Systems | Water and Environmental Lead | Critical | To be assessed | |||
Show details for CLW-024Hide details for CLW-024Task Design treatment, make-up, storage and discharge systems Completion criteria Equipment, capacities, controls, sampling, chemicals, storage, backup, blowdown and discharge satisfy the approved water balance. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Water and Environmental Lead Owns water balance, source legality, quality, treatment, discharge and environmental obligations. Supporting roles Mechanical and Cooling Lead; Civil and Structural Lead; Operations Manager Evidence required Approved water-system P&IDs and calculations Gate or milestone blocked Water-system procurement Risk if delayed Water availability may not translate into reliable usable supply. | |||||||||
| CLW-025 | Validate end-to-end cooling redundancy and failure domains | Detailed Design | Redundancy | Mechanical and Cooling Lead | Critical | To be assessed | |||
Show details for CLW-025Hide details for CLW-025Task Validate end-to-end cooling redundancy and failure domains Completion criteria Equipment, pumps, headers, valves, power feeds, controls, sensors, make-up water and distribution common points are analysed. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Mechanical and Cooling Lead Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria. Supporting roles Electrical Lead; Controls and Monitoring Lead; Insurance and Risk Lead Evidence required Cooling failure-mode and redundancy report Gate or milestone blocked Design freeze Risk if delayed N+1 components may still share a single failure point. | |||||||||
| CLW-026 | Validate isolation, replacement and concurrent maintenance | Detailed Design | Maintainability | Operations Manager | Critical | To be assessed | |||
Show details for CLW-026Hide details for CLW-026Task Validate isolation, replacement and concurrent maintenance Completion criteria Valves, bypasses, clearances, lifting, routes, drains, temporary connections and work procedures support safe maintenance. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Operations Manager Owns operational acceptance, staffing, procedures, monitoring, maintenance and post-handover accountability. Supporting roles Mechanical and Cooling Lead; Lead Architect; HSE Manager Evidence required Operations maintainability review and closed actions Gate or milestone blocked Design freeze Risk if delayed Routine maintenance may require loss of cooling resilience. | |||||||||
| CLW-027 | Design leak detection, containment and drainage | Detailed Design | Leak and Condensation | Mechanical and Cooling Lead | Critical | To be assessed | |||
Show details for CLW-027Hide details for CLW-027Task Design leak detection, containment and drainage Completion criteria Risk areas, sensors, zones, alarms, shutoff logic, trays, drains, waterproofing and condensation controls are defined. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Mechanical and Cooling Lead Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria. Supporting roles Controls and Monitoring Lead; Lead Architect; HSE Manager Evidence required Leak and condensation control design Gate or milestone blocked Design freeze Risk if delayed Water release can damage critical IT and electrical systems. | |||||||||
| CLW-028 | Approve cooling sequence of operations | Detailed Design | Controls | Controls and Monitoring Lead | Critical | To be assessed | |||
Show details for CLW-028Hide details for CLW-028Task Approve cooling sequence of operations Completion criteria Normal, lead-lag, staging, failover, low-water, high-temperature, sensor failure, power return and emergency modes are explicit. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Controls and Monitoring Lead Owns BMS/DCIM/EPMS points, sequences, alarms, integrations, access and reporting. Supporting roles Mechanical and Cooling Lead; Operations Manager; OEM or System Vendor Evidence required Approved sequence of operations Gate or milestone blocked Controls procurement and testing Risk if delayed Controls can cause cascading failure despite adequate equipment. | |||||||||
| CLW-029 | Define metering, sensors, alarms, trends and reports | Detailed Design | Monitoring | Controls and Monitoring Lead | Critical | To be assessed | |||
Show details for CLW-029Hide details for CLW-029Task Define metering, sensors, alarms, trends and reports Completion criteria Temperature, humidity, flow, pressure, energy, water, quality, leak and equipment points have location, accuracy, threshold and retention. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Controls and Monitoring Lead Owns BMS/DCIM/EPMS points, sequences, alarms, integrations, access and reporting. Supporting roles Mechanical and Cooling Lead; Water and Environmental Lead; Operations Manager Evidence required Approved point list, alarm matrix and metering plan Gate or milestone blocked BMS/DCIM implementation Risk if delayed Performance and emerging failures may be invisible. | |||||||||
| CLW-030 | Close cooling and water approval design requirements | Detailed Design | Approvals | Approvals Manager | Critical | To be assessed | |||
Show details for CLW-030Hide details for CLW-030Task Close cooling and water approval design requirements Completion criteria Water, discharge, chemicals, noise, structural, environmental and applicable public-health conditions are incorporated. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Approvals Manager Owns the approval inventory, authority engagement, submissions, conditions, renewals and evidence. Supporting roles Water and Environmental Lead; Mechanical and Cooling Lead; Compliance Manager Evidence required Approval condition compliance matrix Gate or milestone blocked Design freeze / construction Risk if delayed Constructed system may not receive operating permission. | |||||||||
| CLW-031 | Freeze cooling and water design | Detailed Design | Stage Gate | Project Director | Critical | To be assessed | |||
Show details for CLW-031Hide details for CLW-031Task Freeze cooling and water design Completion criteria Loads, equipment, hydraulics, distribution, water, redundancy, maintainability, controls, monitoring and approvals are accepted. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Project Director Owns end-to-end delivery, cross-workstream decisions, executive escalation and stage-gate readiness. Supporting roles Design Manager; Operations Manager; Mechanical and Cooling Lead Evidence required Signed design-freeze certificate and controlled deliverable index Gate or milestone blocked Procurement and construction Risk if delayed Unresolved interfaces become expensive field changes. | |||||||||
| CLW-032 | Issue complete cooling and water procurement specifications | Procurement | Specifications | Procurement Lead | Critical | To be assessed | |||
Show details for CLW-032Hide details for CLW-032Task Issue complete cooling and water procurement specifications Completion criteria Site ratings, materials, controls, FAT/SAT, performance, spares, training, warranty, service and documentation are included. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Procurement Lead Owns sourcing, tendering, commercial closure, contractual obligations and supplier escalation. Supporting roles Mechanical and Cooling Lead; Water and Environmental Lead; Commissioning Manager Evidence required Issued tender package and compliance matrix Gate or milestone blocked Vendor selection Risk if delayed Vendors may offer equipment that meets generic but not project conditions. | |||||||||
| CLW-033 | Evaluate vendor compliance and lifecycle support | Procurement | Evaluation | Procurement Lead | Critical | To be assessed | |||
Show details for CLW-033Hide details for CLW-033Task Evaluate vendor compliance and lifecycle support Completion criteria Technical deviations, performance curves, materials, control interfaces, references, lead time, local service and lifecycle cost are assessed. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Procurement Lead Owns sourcing, tendering, commercial closure, contractual obligations and supplier escalation. Supporting roles Mechanical and Cooling Lead; Operations Manager; Finance and Commercial Lead Evidence required Approved technical-commercial evaluation Gate or milestone blocked Contract award Risk if delayed Low bid may have weak local support or hidden derating. | |||||||||
| CLW-034 | Award with performance, testing and support obligations | Procurement | Contracting | Procurement Lead | Critical | To be assessed | |||
Show details for CLW-034Hide details for CLW-034Task Award with performance, testing and support obligations Completion criteria Contracts include guaranteed conditions, FAT/SAT, load tests, commissioning attendance, training, spares, warranty, AMC and remedies. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Procurement Lead Owns sourcing, tendering, commercial closure, contractual obligations and supplier escalation. Supporting roles Legal Counsel; Commissioning Manager; Finance and Commercial Lead Evidence required Executed contracts and responsibility matrix Gate or milestone blocked Manufacturing Risk if delayed Performance gaps may lack contractual remedy. | |||||||||
| CLW-035 | Approve and witness critical equipment FAT | Factory Testing | FAT | Commissioning Manager | High | To be assessed | |||
Show details for CLW-035Hide details for CLW-035Task Approve and witness critical equipment FAT Completion criteria Approved procedures test controls, safeties, performance-relevant functions and interfaces; deviations are closed or transferred. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Commissioning Manager Owns commissioning strategy, test plans, witnesses, execution, defects, retests and evidence. Supporting roles Mechanical and Cooling Lead; Quality Manager; OEM or System Vendor Evidence required Signed FAT reports and defect closure Gate or milestone blocked Shipment release Risk if delayed Defects may reach site and consume commissioning contingency. | |||||||||
| CLW-036 | Inspect cooling and water installation | Construction | Installation | Quality Manager | Critical | To be assessed | |||
Show details for CLW-036Hide details for CLW-036Task Inspect cooling and water installation Completion criteria Equipment, supports, pipework, slopes, valves, insulation, drains, sensors, labels, access, cleanliness and corrosion protection comply. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Quality Manager Owns inspection plans, quality records, non-conformance, snag closure and evidence quality. Supporting roles Construction Manager; Mechanical and Cooling Lead; Water and Environmental Lead Evidence required Installation inspection records Gate or milestone blocked Pressure test and flushing Risk if delayed Installation defects can cause leaks, contamination or low flow. | |||||||||
| CLW-037 | Complete pressure tests, flushing and cleaning | Construction | Testing | Mechanical and Cooling Lead | Critical | To be assessed | |||
Show details for CLW-037Hide details for CLW-037Task Complete pressure tests, flushing and cleaning Completion criteria Systems pass approved pressure/leak tests and cleanliness criteria; flushing records and water disposal evidence are complete. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Mechanical and Cooling Lead Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria. Supporting roles Quality Manager; Commissioning Manager; Water and Environmental Lead Evidence required Pressure, flushing and cleanliness reports Gate or milestone blocked Wet commissioning Risk if delayed Debris or leakage can damage equipment. | |||||||||
| CLW-038 | Commission treatment and establish baseline chemistry | Construction | Water Treatment | Water and Environmental Lead | Critical | To be assessed | |||
Show details for CLW-038Hide details for CLW-038Task Commission treatment and establish baseline chemistry Completion criteria Treatment equipment operates, dosing is controlled, water meets limits and sampling/response procedure is active. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Water and Environmental Lead Owns water balance, source legality, quality, treatment, discharge and environmental obligations. Supporting roles Mechanical and Cooling Lead; OEM or System Vendor; Operations Manager Evidence required Commissioning results and baseline laboratory report Gate or milestone blocked Cooling functional testing Risk if delayed Untreated water can immediately foul or corrode systems. | |||||||||
| CLW-039 | Test pumps, valves and hydraulic performance | Commissioning | Functional | Mechanical and Cooling Lead | Critical | To be assessed | |||
Show details for CLW-039Hide details for CLW-039Task Test pumps, valves and hydraulic performance Completion criteria Duty/standby, flows, pressures, balancing, isolation, lead-lag, alarms and operating points meet design. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Mechanical and Cooling Lead Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria. Supporting roles Commissioning Manager; Controls and Monitoring Lead; OEM or System Vendor Evidence required Signed hydraulic functional and balancing report Gate or milestone blocked Cooling system acceptance Risk if delayed System may not deliver required flow or redundancy. | |||||||||
| CLW-040 | Test primary and terminal cooling equipment | Commissioning | Functional | Commissioning Manager | Critical | To be assessed | |||
Show details for CLW-040Hide details for CLW-040Task Test primary and terminal cooling equipment Completion criteria Capacity-relevant operation, safeties, turndown, controls, alarms, restart, airflow and room response pass. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Commissioning Manager Owns commissioning strategy, test plans, witnesses, execution, defects, retests and evidence. Supporting roles Mechanical and Cooling Lead; OEM or System Vendor; Operations Manager Evidence required Signed equipment functional test reports Gate or milestone blocked Thermal load test Risk if delayed Equipment may not achieve site performance. | |||||||||
| CLW-041 | Test sequences, failover and post-power recovery | Commissioning | Controls | Controls and Monitoring Lead | Critical | To be assessed | |||
Show details for CLW-041Hide details for CLW-041Task Test sequences, failover and post-power recovery Completion criteria Lead-lag, staging, component failure, controller/sensor failure, power interruption and restoration follow approved sequence. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Controls and Monitoring Lead Owns BMS/DCIM/EPMS points, sequences, alarms, integrations, access and reporting. Supporting roles Commissioning Manager; Mechanical and Cooling Lead; Operations Manager Evidence required Signed sequence and failover test report Gate or milestone blocked Integrated cooling test Risk if delayed Control logic may defeat physical redundancy. | |||||||||
| CLW-042 | Test water storage, make-up, low-water and backup supply | Commissioning | Water Resilience | Water and Environmental Lead | Critical | To be assessed | |||
Show details for CLW-042Hide details for CLW-042Task Test water storage, make-up, low-water and backup supply Completion criteria Levels, replenishment, source changeover, low-water alarms, emergency connections and response meet required autonomy. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Water and Environmental Lead Owns water balance, source legality, quality, treatment, discharge and environmental obligations. Supporting roles Commissioning Manager; Operations Manager; Security Lead Evidence required Signed water resilience test report Gate or milestone blocked Cooling resilience acceptance Risk if delayed Cooling may stop during source interruption. | |||||||||
| CLW-043 | Test leak detection, containment, isolation and escalation | Commissioning | Leak Detection | Commissioning Manager | Critical | To be assessed | |||
Show details for CLW-043Hide details for CLW-043Task Test leak detection, containment, isolation and escalation Completion criteria Representative leaks trigger correct zone, alarm, notification, shutoff/response and safe recovery without unintended impact. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Commissioning Manager Owns commissioning strategy, test plans, witnesses, execution, defects, retests and evidence. Supporting roles Controls and Monitoring Lead; Operations Manager; HSE Manager Evidence required Signed leak scenario test report Gate or milestone blocked Environmental and operations acceptance Risk if delayed Leak controls may fail when IT equipment is exposed. | |||||||||
| CLW-044 | Execute staged thermal load test | Commissioning | Thermal Load | Commissioning Authority | Critical | To be assessed | |||
Show details for CLW-044Hide details for CLW-044Task Execute staged thermal load test Completion criteria Approved load, density, duration and ambient conditions produce acceptable rack inlet temperatures, humidity, flow, pressure and stability. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Commissioning Authority Independently challenges test scope, witnesses critical tests and validates readiness and results. Supporting roles Commissioning Manager; Mechanical and Cooling Lead; Operations Manager Evidence required Thermal load report and trend data Gate or milestone blocked Cooling acceptance Risk if delayed Cooling performance under realistic IT load remains unproven. | |||||||||
| CLW-045 | Test component loss and high-temperature response | Commissioning | Failure Scenarios | Commissioning Manager | Critical | To be assessed | |||
Show details for CLW-045Hide details for CLW-045Task Test component loss and high-temperature response Completion criteria Specified unit, pump, control or source failures maintain conditions within design or trigger timely controlled response and recovery. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Commissioning Manager Owns commissioning strategy, test plans, witnesses, execution, defects, retests and evidence. Supporting roles Mechanical and Cooling Lead; Controls and Monitoring Lead; Operations Manager Evidence required Signed cooling failure-scenario reports Gate or milestone blocked Cooling resilience acceptance Risk if delayed Installed N+1 may not work in practice. | |||||||||
| CLW-046 | Validate energy and water metering and KPI calculations | Commissioning | Efficiency | Controls and Monitoring Lead | High | To be assessed | |||
Show details for CLW-046Hide details for CLW-046Task Validate energy and water metering and KPI calculations Completion criteria Meters are accurate, boundaries match definitions and PUE/WUE-related cooling inputs can be calculated from retained data. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Controls and Monitoring Lead Owns BMS/DCIM/EPMS points, sequences, alarms, integrations, access and reporting. Supporting roles Mechanical and Cooling Lead; Water and Environmental Lead; Operations Manager Evidence required Meter validation and KPI calculation report Gate or milestone blocked Sustainability reporting Risk if delayed Efficiency claims may be wrong or impossible to improve. | |||||||||
| CLW-047 | Close cooling and water defects with retest evidence | Commissioning | Defects | Quality Manager | Critical | To be assessed | |||
Show details for CLW-047Hide details for CLW-047Task Close cooling and water defects with retest evidence Completion criteria All critical defects close; corrections are retested; affected interfaces regress; remaining risk has authorised acceptance. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Quality Manager Owns inspection plans, quality records, non-conformance, snag closure and evidence quality. Supporting roles Commissioning Manager; Mechanical and Cooling Lead; Operations Manager Evidence required Final defect register and signed retest evidence Gate or milestone blocked Cooling acceptance Risk if delayed Known defects may become operational failures. | |||||||||
| CLW-048 | Approve cooling and water commissioning acceptance | Commissioning | Stage Gate | Project Director | Critical | To be assessed | |||
Show details for CLW-048Hide details for CLW-048Task Approve cooling and water commissioning acceptance Completion criteria Functional, resilience, thermal, leak, water and monitoring tests pass; evidence and residual-risk acceptance are complete. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Project Director Owns end-to-end delivery, cross-workstream decisions, executive escalation and stage-gate readiness. Supporting roles Commissioning Authority; Operations Manager; Water and Environmental Lead Evidence required Signed cooling and water acceptance certificate Gate or milestone blocked Operations handover Risk if delayed Critical environmental systems may be handed over unproven. | |||||||||
| CLW-049 | Approve cooling and water SOPs, MOPs and EOPs | Operations Readiness | Procedures | Operations Manager | Critical | To be assessed | |||
Show details for CLW-049Hide details for CLW-049Task Approve cooling and water SOPs, MOPs and EOPs Completion criteria Routine operation, chemistry, isolation, maintenance, high temperature, component failure, water shortage and leak procedures are validated. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Operations Manager Owns operational acceptance, staffing, procedures, monitoring, maintenance and post-handover accountability. Supporting roles Facilities Manager; Water and Environmental Lead; HSE Manager; Document Controller Evidence required Approved and field-validated procedure set Gate or milestone blocked Operational acceptance Risk if delayed Staff may improvise during fast-moving environmental events. | |||||||||
| CLW-050 | Activate maintenance, vendor support and spares | Operations Readiness | Maintenance | Facilities Manager | Critical | To be assessed | |||
Show details for CLW-050Hide details for CLW-050Task Activate maintenance, vendor support and spares Completion criteria Preventive plan, statutory tasks, AMCs, emergency contacts, chemicals, consumables, tools and critical spares are available. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Facilities Manager Owns daily critical-facility operation, maintenance readiness, spares, rounds and emergency response. Supporting roles Procurement Lead; OEM or System Vendor; Operations Manager Evidence required Maintenance calendar, contracts and physical inventory Gate or milestone blocked Operational acceptance Risk if delayed Small component or chemistry failure may extend outage. | |||||||||
| CLW-051 | Train and assess cooling and water operators | Operations Readiness | Training | Operations Manager | Critical | To be assessed | |||
Show details for CLW-051Hide details for CLW-051Task Train and assess cooling and water operators Completion criteria Assigned personnel demonstrate normal rounds, chemistry checks, alarm response, isolation, leak response and escalation. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Operations Manager Owns operational acceptance, staffing, procedures, monitoring, maintenance and post-handover accountability. Supporting roles HR and Training Lead; Mechanical and Cooling Lead; Water and Environmental Lead Evidence required Training and practical competency records Gate or milestone blocked Operational acceptance Risk if delayed Operators may not recognise deterioration or respond safely. | |||||||||
| CLW-052 | Activate water, discharge and environmental compliance calendar | Operations Readiness | Compliance | Compliance Manager | Critical | To be assessed | |||
Show details for CLW-052Hide details for CLW-052Task Activate water, discharge and environmental compliance calendar Completion criteria Sampling, consumption, discharge, chemical, approval-condition and renewal obligations have dates, owners and evidence locations. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Compliance Manager Owns compliance obligations, evidence retention, renewals, audits and controlled exceptions. Supporting roles Water and Environmental Lead; Operations Manager; Document Controller Evidence required Operational compliance calendar Gate or milestone blocked Operational go-live Risk if delayed Missed conditions may trigger penalties or supply restrictions. | |||||||||
| CLW-053 | Baseline operating trends and alarm response | Operations Readiness | Monitoring | Operations Manager | High | To be assessed | |||
Show details for CLW-053Hide details for CLW-053Task Baseline operating trends and alarm response Completion criteria Normal temperature, humidity, energy, water, chemistry, flow and pressure trends are captured; alarm escalation is tested. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Operations Manager Owns operational acceptance, staffing, procedures, monitoring, maintenance and post-handover accountability. Supporting roles Controls and Monitoring Lead; Facilities Manager Evidence required Baseline trend pack and alarm test report Gate or milestone blocked Stabilisation Risk if delayed Operations may lack reference data for early fault detection. | |||||||||
| CLW-054 | Run seasonal performance and capacity review | Stabilisation | Optimisation | Operations Manager | High | To be assessed | |||
Show details for CLW-054Hide details for CLW-054Task Run seasonal performance and capacity review Completion criteria Actual load, PUE/WUE inputs, water quality, alarms, redundancy use, maintenance and peak-condition performance are compared with design. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Operations Manager Owns operational acceptance, staffing, procedures, monitoring, maintenance and post-handover accountability. Supporting roles Mechanical and Cooling Lead; Water and Environmental Lead; Finance and Commercial Lead Evidence required Seasonal performance report and action register Gate or milestone blocked Optimisation / next expansion phase Risk if delayed Design assumptions may remain uncorrected as load grows. | |||||||||
| CLW-055 | Revalidate cooling and water plan before each expansion phase | Stabilisation | Expansion | Mechanical and Cooling Lead | Critical | To be assessed | |||
Show details for CLW-055Hide details for CLW-055Task Revalidate cooling and water plan before each expansion phase Completion criteria Actual performance, source availability, approvals, capacity headroom, density and lessons learned update the next-phase design. Dependency explanation Predecessor tasks provide the approved input, evidence or readiness required for this task. Accountable role Mechanical and Cooling Lead Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria. Supporting roles Operations Manager; Water and Environmental Lead; Design Manager Evidence required Approved expansion readiness review Gate or milestone blocked Next capacity release Risk if delayed Later phases may repeat obsolete assumptions or exhaust site resources. | |||||||||