Data Center Project Management

Data Center Cooling and Water Planning Checklist — India

Load and climate basis, water source and quality, technology selection, detailed design, procurement, installation, testing, and operations for cooling and water planning.

Source article: Data Center Cooling and Water Planning in India·
Share
55
Total tasks
46
Critical tasks
12
Phases
50
Workstreams
15
Accountable owner roles
This checklist is a project-management framework, not legal, regulatory, engineering or certification advice. Exact requirements vary by location, authority, facility design, operating model and project objectives. Validate applicability with qualified local professionals and the relevant authorities. Completing the checklist does not guarantee approval, certification, uptime or regulatory compliance.

How to use this tracker

Each row is an executable work package. Assign a named individual against the accountable role, enter planned start and end dates, follow the predecessor task IDs, and mark a task complete only when its completion criterion is met and supporting evidence has been reviewed.

The owner column deliberately contains the accountable role, not a person’s name, so the tracker stays reusable across organisations. Add a Named_Ownercolumn — or use the local “Named owner” field on each task below — in your working copy.

Using it in Excel

  1. Import the file as UTF-8.
  2. Convert the imported range into an Excel Table.
  3. Freeze the header row.
  4. Use ISO dates in YYYY-MM-DD format.
  5. Add data-validation lists for Status and Applicability.
  6. Filter Critical tasks and blocked project gates during every project review.
  7. Add a Named_Owner column in the working copy.
  8. Record the accepting authority in Notes for Accepted Risk.
  9. Preserve stable Task IDs when customising the tracker.
  10. Do not mark a task complete until its evidence has been reviewed.

Status legend

Not Started
No work has begun on this task yet.
In Progress
Work is underway but the completion criterion is not yet met.
Complete
The completion criterion has been met and supporting evidence has been reviewed. Do not mark a task Complete only because the activity occurred.
Blocked
The task cannot proceed. Record the blocker in Notes.
Not Applicable
Record the reason and the approving authority in Notes.
Accepted Risk
Record the accepting authority, the interim control and the review date in Notes.

Applicability legend

Required
This task applies to the project as scoped.
Conditional
Applicability depends on site, authority, technology, or scope decisions not yet made.
Not Applicable
Confirmed out of scope for this project — record the reason in Notes.
To be assessed
Applicability has not yet been evaluated for this project.

Priority (Critical, High, Medium, Low) and Applicability are always shown as text, never by colour alone.

The complete tracker — 55 tasks

0 / 55
Complete
0%
Percent complete
46
Critical open
0
Blocked
0
Not Applicable (excluded from %)
0
Accepted Risk (open, not counted complete)
54
Tasks with unmet predecessors
55 of 55
Showing

Percent complete = Complete ÷ (Total − Not Applicable). Not Applicable tasks are removed from the denominator because they are out of scope; Accepted Risk tasks stay in the denominator but are never counted as complete, so accepted risk is always visible rather than hidden inside the percentage.

Download blank CSV

Loading saved progress…

Task IDTaskPhaseWorkstreamOwner roleDepends onStatusPriorityApplicabilityDetails
CLW-001Appoint cooling and water workstream ownerInitiationGovernanceMechanical and Cooling LeadCriticalTo be assessed
Show details for CLW-001
Task
Appoint cooling and water workstream owner
Completion criteria
Named owner controls requirements, option evaluation, design interfaces, water evidence, approvals, testing and operations readiness.
Dependency explanation
Starting task.
Accountable role
Mechanical and Cooling Lead
Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria.
Supporting roles
Project Director; Water and Environmental Lead; PMO Lead
Evidence required
Approved appointment and RACI
Gate or milestone blocked
Cooling and water mobilisation
Risk if delayed
Power, cooling, water and site decisions may diverge.
CLW-002Approve phased IT heat-load and density modelRequirementsIT LoadDesign Manager
CriticalTo be assessed
Show details for CLW-002
Task
Approve phased IT heat-load and density model
Completion criteria
Day-one/full-build load, diversity, average/peak rack density, AI zones and growth assumptions are approved.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Design Manager
Coordinates multidisciplinary design, interfaces, reviews, change control and design freeze.
Supporting roles
Mechanical and Cooling Lead; Electrical Lead; IT and Network Lead
Evidence required
Approved IT load and density model
Gate or milestone blocked
Cooling feasibility
Risk if delayed
Plant and distribution may be incorrectly sized.
CLW-003Define operating environmental and resilience requirementsRequirementsEnvironmental EnvelopeMechanical and Cooling Lead
CriticalTo be assessed
Show details for CLW-003
Task
Define operating environmental and resilience requirements
Completion criteria
Temperature, humidity, allowable excursions, redundancy, maintainability, recovery and monitoring requirements are approved.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Mechanical and Cooling Lead
Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria.
Supporting roles
Operations Manager; Design Manager; Insurance and Risk Lead
Evidence required
Approved environmental design criteria
Gate or milestone blocked
Cooling concept
Risk if delayed
Different teams may use inconsistent performance criteria.
CLW-004Compile site-specific climate design dataSite InputsClimateMechanical and Cooling Lead
CriticalTo be assessed
Show details for CLW-004
Task
Compile site-specific climate design data
Completion criteria
Peak dry-bulb, wet-bulb, humidity, heat wave, monsoon, dust, air quality and corrosion conditions are documented.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Mechanical and Cooling Lead
Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria.
Supporting roles
Water and Environmental Lead; Insurance and Risk Lead
Evidence required
Climate design-condition report
Gate or milestone blocked
Technology screening
Risk if delayed
Favourable averages may conceal peak-condition failure.
CLW-005Document site, space and utility constraintsSite InputsConstraintsLead Architect
HighTo be assessed
Show details for CLW-005
Task
Document site, space and utility constraints
Completion criteria
Available plant space, roofs/yards, heights, loads, acoustic limits, electrical capacity, access, phasing and replacement routes are known.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Lead Architect
Owns architectural compliance, building submissions, space planning and authority drawing coordination.
Supporting roles
Mechanical and Cooling Lead; Electrical Lead; Civil and Structural Lead; Operations Manager
Evidence required
Site constraint and interface register
Gate or milestone blocked
Cooling concept
Risk if delayed
Selected technology may not physically fit or be maintainable.
CLW-006Calculate day-one and full-build water demandWater FeasibilityDemandWater and Environmental Lead
CriticalTo be assessed
Show details for CLW-006
Task
Calculate day-one and full-build water demand
Completion criteria
Cooling make-up, blowdown, treatment, domestic, fire and contingency demands are calculated by season and operating mode.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Water and Environmental Lead
Owns water balance, source legality, quality, treatment, discharge and environmental obligations.
Supporting roles
Mechanical and Cooling Lead; Fire and Life Safety Consultant
Evidence required
Approved water balance
Gate or milestone blocked
Water-source diligence
Risk if delayed
Source adequacy and permissions cannot be evaluated.
CLW-007Identify primary, secondary and emergency water sourcesWater FeasibilitySourceWater and Environmental Lead
CriticalTo be assessed
Show details for CLW-007
Task
Identify primary, secondary and emergency water sources
Completion criteria
Every proposed source has location, provider, legal basis, quantity, seasonality, delivery method and expansion potential.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Water and Environmental Lead
Owns water balance, source legality, quality, treatment, discharge and environmental obligations.
Supporting roles
Legal Counsel; Approvals Manager; Finance and Commercial Lead
Evidence required
Water-source register
Gate or milestone blocked
Source validation
Risk if delayed
Project may rely on one undocumented or fragile source.
CLW-008Validate legal right, allocation and approval pathWater FeasibilityLegal and ApprovalsApprovals Manager
CriticalTo be assessed
Show details for CLW-008
Task
Validate legal right, allocation and approval path
Completion criteria
Supply agreements, permitted quantity, groundwater applicability, authority approvals and continuing conditions are confirmed.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Approvals Manager
Owns the approval inventory, authority engagement, submissions, conditions, renewals and evidence.
Supporting roles
Water and Environmental Lead; Legal Counsel; Compliance Manager
Evidence required
Legal and approval feasibility memorandum
Gate or milestone blocked
Technology selection / site commitment
Risk if delayed
Cooling may depend on unlawful abstraction or uncertain supply.
CLW-009Assess seasonal availability and drought riskWater FeasibilityReliabilityWater and Environmental Lead
CriticalTo be assessed
Show details for CLW-009
Task
Assess seasonal availability and drought risk
Completion criteria
Historical restrictions, competing demand, drought periods, provider outages and climate trends are reflected in source reliability.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Water and Environmental Lead
Owns water balance, source legality, quality, treatment, discharge and environmental obligations.
Supporting roles
Insurance and Risk Lead; Operations Manager
Evidence required
Seasonal water reliability assessment
Gate or milestone blocked
Water resilience design
Risk if delayed
Annual supply volume can hide critical summer shortages.
CLW-010Complete representative source-water testingWater FeasibilityQualityWater and Environmental Lead
HighTo be assessed
Show details for CLW-010
Task
Complete representative source-water testing
Completion criteria
Tests cover hardness, conductivity, chlorides, silica, pH, suspended solids, biological and other treatment-relevant parameters.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Water and Environmental Lead
Owns water balance, source legality, quality, treatment, discharge and environmental obligations.
Supporting roles
Mechanical and Cooling Lead; Quality Manager
Evidence required
Accredited laboratory reports
Gate or milestone blocked
Treatment design
Risk if delayed
Scaling, corrosion or fouling may be underestimated.
CLW-011Define water-treatment and chemistry requirementsWater FeasibilityTreatmentWater and Environmental Lead
CriticalTo be assessed
Show details for CLW-011
Task
Define water-treatment and chemistry requirements
Completion criteria
Filtration, softening, dosing, cycles of concentration, biological control, monitoring and consumables are defined from test results.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Water and Environmental Lead
Owns water balance, source legality, quality, treatment, discharge and environmental obligations.
Supporting roles
Mechanical and Cooling Lead; Operations Manager; OEM or System Vendor
Evidence required
Water treatment basis and chemistry limits
Gate or milestone blocked
Technology and equipment selection
Risk if delayed
Incorrect chemistry can damage plant and increase water use.
CLW-012Define storage and emergency replenishment strategyWater FeasibilityStorage and BackupWater and Environmental Lead
CriticalTo be assessed
Show details for CLW-012
Task
Define storage and emergency replenishment strategy
Completion criteria
Required autonomy, storage volumes, segregation, refill rates, tanker logistics, connection points and emergency contracts are documented.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Water and Environmental Lead
Owns water balance, source legality, quality, treatment, discharge and environmental obligations.
Supporting roles
Lead Architect; Operations Manager; Security Lead
Evidence required
Approved storage and backup strategy
Gate or milestone blocked
Site layout and water resilience
Risk if delayed
Cooling may fail before emergency water arrives.
CLW-013Validate blowdown, wastewater and drainage routeWater FeasibilityDischargeWater and Environmental Lead
CriticalTo be assessed
Show details for CLW-013
Task
Validate blowdown, wastewater and drainage route
Completion criteria
Quantities, quality, treatment, sewer/discharge path, permissions, sampling and seasonal constraints are confirmed.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Water and Environmental Lead
Owns water balance, source legality, quality, treatment, discharge and environmental obligations.
Supporting roles
Approvals Manager; Civil and Structural Lead; Legal Counsel
Evidence required
Discharge feasibility and approval note
Gate or milestone blocked
Cooling concept / environmental approval
Risk if delayed
No lawful or practical disposal route may exist.
CLW-014Create cooling technology option setConcept SelectionOptionsMechanical and Cooling Lead
HighTo be assessed
Show details for CLW-014
Task
Create cooling technology option set
Completion criteria
Applicable air, DX, chilled-water, dry, evaporative, hybrid, rear-door, direct-to-chip and immersion options are identified.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Mechanical and Cooling Lead
Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria.
Supporting roles
Design Manager; Operations Manager; OEM or System Vendor
Evidence required
Cooling technology longlist
Gate or milestone blocked
Option evaluation
Risk if delayed
Team may prematurely select a familiar technology.
CLW-015Compare options for technical and site fitConcept SelectionEvaluationMechanical and Cooling Lead
CriticalTo be assessed
Show details for CLW-015
Task
Compare options for technical and site fit
Completion criteria
Each option is scored for density, climate, peak performance, water, power, space, redundancy, maintenance, support and expansion.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Mechanical and Cooling Lead
Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria.
Supporting roles
Electrical Lead; Water and Environmental Lead; Operations Manager; Insurance and Risk Lead
Evidence required
Evidence-linked technology scorecard
Gate or milestone blocked
Concept selection
Risk if delayed
A lower-PUE option may create unacceptable water or operational risk.
CLW-016Compare lifecycle energy, water and maintenance costConcept SelectionLifecycle CostFinance and Commercial Lead
HighTo be assessed
Show details for CLW-016
Task
Compare lifecycle energy, water and maintenance cost
Completion criteria
Capex, peak and part-load energy, water, treatment, chemicals, staffing, service, replacement and risk contingencies use common assumptions.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Finance and Commercial Lead
Owns cost, lifecycle economics, commercial assumptions, incentives and financial validation.
Supporting roles
Mechanical and Cooling Lead; Water and Environmental Lead; Operations Manager
Evidence required
Lifecycle cost comparison
Gate or milestone blocked
Concept approval
Risk if delayed
Low initial cost may produce high operating expense.
CLW-017Set evidence-based PUE and WUE targetsConcept SelectionSustainabilityMechanical and Cooling Lead
HighTo be assessed
Show details for CLW-017
Task
Set evidence-based PUE and WUE targets
Completion criteria
Targets specify boundary, load level, climate basis, measurement points, exclusions and reporting method.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Mechanical and Cooling Lead
Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria.
Supporting roles
Water and Environmental Lead; Controls and Monitoring Lead; Finance and Commercial Lead
Evidence required
Approved efficiency KPI definition
Gate or milestone blocked
Concept approval
Risk if delayed
Marketing targets may be unmeasurable or achieved by shifting resource use.
CLW-018Approve cooling and water conceptConcept SelectionDecisionProject Director
CriticalTo be assessed
Show details for CLW-018
Task
Approve cooling and water concept
Completion criteria
Decision authority accepts selected technology, water dependency, power impact, lifecycle cost, resilience, risks and expansion approach.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Project Director
Owns end-to-end delivery, cross-workstream decisions, executive escalation and stage-gate readiness.
Supporting roles
Mechanical and Cooling Lead; Operations Manager; Finance and Commercial Lead
Evidence required
Signed concept decision memorandum
Gate or milestone blocked
Detailed design
Risk if delayed
Major plant architecture may be locked without explicit trade-off acceptance.
CLW-019Complete detailed cooling load and diversity modelDetailed DesignLoad ModelMechanical and Cooling Lead
CriticalTo be assessed
Show details for CLW-019
Task
Complete detailed cooling load and diversity model
Completion criteria
IT, UPS, electrical, people, lighting, envelope, infiltration and future loads are calculated by zone and phase.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Mechanical and Cooling Lead
Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria.
Supporting roles
Electrical Lead; Lead Architect; Design Manager
Evidence required
Reviewed cooling load calculation
Gate or milestone blocked
Equipment sizing
Risk if delayed
System may be undersized, oversized or poorly phased.
CLW-020Select primary cooling equipment at site conditionsDetailed DesignEquipmentMechanical and Cooling Lead
CriticalTo be assessed
Show details for CLW-020
Task
Select primary cooling equipment at site conditions
Completion criteria
Capacity, turndown, efficiency, redundancy, ambient derating, sound, materials and maintainability meet approved criteria.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Mechanical and Cooling Lead
Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria.
Supporting roles
OEM or System Vendor; Operations Manager; Electrical Lead
Evidence required
Approved equipment selection schedules
Gate or milestone blocked
Procurement release
Risk if delayed
Catalogue ratings may not apply at local peak conditions.
CLW-021Complete hydraulic design and calculationsDetailed DesignHydraulicsMechanical and Cooling Lead
CriticalTo be assessed
Show details for CLW-021
Task
Complete hydraulic design and calculations
Completion criteria
Pipe sizes, flows, pressure drops, pump head, expansion, water volume, balancing and transient considerations are approved.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Mechanical and Cooling Lead
Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria.
Supporting roles
Design Manager; OEM or System Vendor
Evidence required
Reviewed hydraulic calculations and P&IDs
Gate or milestone blocked
Mechanical IFC release
Risk if delayed
Poor flow or pressure can defeat cooling capacity.
CLW-022Complete room and rack air-distribution designDetailed DesignAir DistributionMechanical and Cooling Lead
CriticalTo be assessed
Show details for CLW-022
Task
Complete room and rack air-distribution design
Completion criteria
Airflow, containment, pressure, return paths, blanking, leakage and high-density zones maintain required rack inlet conditions.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Mechanical and Cooling Lead
Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria.
Supporting roles
Lead Architect; IT and Network Lead; Operations Manager
Evidence required
CFD/airflow analysis or approved distribution design
Gate or milestone blocked
White-space IFC release
Risk if delayed
Plant capacity may not reach the racks that need it.
CLW-023Define high-density liquid-cooling interfacesDetailed DesignLiquid CoolingMechanical and Cooling Lead
CriticalConditional
Show details for CLW-023
Task
Define high-density liquid-cooling interfaces
Completion criteria
CDUs, facility water interface, pressure, temperature, chemistry, redundancy, leak containment, drains and ownership are defined.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Mechanical and Cooling Lead
Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria.
Supporting roles
IT and Network Lead; OEM or System Vendor; Water and Environmental Lead
Evidence required
Approved liquid-cooling interface specification
Gate or milestone blocked
High-density procurement and fit-out
Risk if delayed
IT and facility systems may have incompatible limits.
CLW-024Design treatment, make-up, storage and discharge systemsDetailed DesignWater SystemsWater and Environmental Lead
CriticalTo be assessed
Show details for CLW-024
Task
Design treatment, make-up, storage and discharge systems
Completion criteria
Equipment, capacities, controls, sampling, chemicals, storage, backup, blowdown and discharge satisfy the approved water balance.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Water and Environmental Lead
Owns water balance, source legality, quality, treatment, discharge and environmental obligations.
Supporting roles
Mechanical and Cooling Lead; Civil and Structural Lead; Operations Manager
Evidence required
Approved water-system P&IDs and calculations
Gate or milestone blocked
Water-system procurement
Risk if delayed
Water availability may not translate into reliable usable supply.
CLW-025Validate end-to-end cooling redundancy and failure domainsDetailed DesignRedundancyMechanical and Cooling Lead
CriticalTo be assessed
Show details for CLW-025
Task
Validate end-to-end cooling redundancy and failure domains
Completion criteria
Equipment, pumps, headers, valves, power feeds, controls, sensors, make-up water and distribution common points are analysed.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Mechanical and Cooling Lead
Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria.
Supporting roles
Electrical Lead; Controls and Monitoring Lead; Insurance and Risk Lead
Evidence required
Cooling failure-mode and redundancy report
Gate or milestone blocked
Design freeze
Risk if delayed
N+1 components may still share a single failure point.
CLW-026Validate isolation, replacement and concurrent maintenanceDetailed DesignMaintainabilityOperations Manager
CriticalTo be assessed
Show details for CLW-026
Task
Validate isolation, replacement and concurrent maintenance
Completion criteria
Valves, bypasses, clearances, lifting, routes, drains, temporary connections and work procedures support safe maintenance.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Operations Manager
Owns operational acceptance, staffing, procedures, monitoring, maintenance and post-handover accountability.
Supporting roles
Mechanical and Cooling Lead; Lead Architect; HSE Manager
Evidence required
Operations maintainability review and closed actions
Gate or milestone blocked
Design freeze
Risk if delayed
Routine maintenance may require loss of cooling resilience.
CLW-027Design leak detection, containment and drainageDetailed DesignLeak and CondensationMechanical and Cooling Lead
CriticalTo be assessed
Show details for CLW-027
Task
Design leak detection, containment and drainage
Completion criteria
Risk areas, sensors, zones, alarms, shutoff logic, trays, drains, waterproofing and condensation controls are defined.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Mechanical and Cooling Lead
Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria.
Supporting roles
Controls and Monitoring Lead; Lead Architect; HSE Manager
Evidence required
Leak and condensation control design
Gate or milestone blocked
Design freeze
Risk if delayed
Water release can damage critical IT and electrical systems.
CLW-028Approve cooling sequence of operationsDetailed DesignControlsControls and Monitoring Lead
CriticalTo be assessed
Show details for CLW-028
Task
Approve cooling sequence of operations
Completion criteria
Normal, lead-lag, staging, failover, low-water, high-temperature, sensor failure, power return and emergency modes are explicit.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Controls and Monitoring Lead
Owns BMS/DCIM/EPMS points, sequences, alarms, integrations, access and reporting.
Supporting roles
Mechanical and Cooling Lead; Operations Manager; OEM or System Vendor
Evidence required
Approved sequence of operations
Gate or milestone blocked
Controls procurement and testing
Risk if delayed
Controls can cause cascading failure despite adequate equipment.
CLW-029Define metering, sensors, alarms, trends and reportsDetailed DesignMonitoringControls and Monitoring Lead
CriticalTo be assessed
Show details for CLW-029
Task
Define metering, sensors, alarms, trends and reports
Completion criteria
Temperature, humidity, flow, pressure, energy, water, quality, leak and equipment points have location, accuracy, threshold and retention.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Controls and Monitoring Lead
Owns BMS/DCIM/EPMS points, sequences, alarms, integrations, access and reporting.
Supporting roles
Mechanical and Cooling Lead; Water and Environmental Lead; Operations Manager
Evidence required
Approved point list, alarm matrix and metering plan
Gate or milestone blocked
BMS/DCIM implementation
Risk if delayed
Performance and emerging failures may be invisible.
CLW-030Close cooling and water approval design requirementsDetailed DesignApprovalsApprovals Manager
CriticalTo be assessed
Show details for CLW-030
Task
Close cooling and water approval design requirements
Completion criteria
Water, discharge, chemicals, noise, structural, environmental and applicable public-health conditions are incorporated.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Approvals Manager
Owns the approval inventory, authority engagement, submissions, conditions, renewals and evidence.
Supporting roles
Water and Environmental Lead; Mechanical and Cooling Lead; Compliance Manager
Evidence required
Approval condition compliance matrix
Gate or milestone blocked
Design freeze / construction
Risk if delayed
Constructed system may not receive operating permission.
CLW-031Freeze cooling and water designDetailed DesignStage GateProject Director
CriticalTo be assessed
Show details for CLW-031
Task
Freeze cooling and water design
Completion criteria
Loads, equipment, hydraulics, distribution, water, redundancy, maintainability, controls, monitoring and approvals are accepted.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Project Director
Owns end-to-end delivery, cross-workstream decisions, executive escalation and stage-gate readiness.
Supporting roles
Design Manager; Operations Manager; Mechanical and Cooling Lead
Evidence required
Signed design-freeze certificate and controlled deliverable index
Gate or milestone blocked
Procurement and construction
Risk if delayed
Unresolved interfaces become expensive field changes.
CLW-032Issue complete cooling and water procurement specificationsProcurementSpecificationsProcurement Lead
CriticalTo be assessed
Show details for CLW-032
Task
Issue complete cooling and water procurement specifications
Completion criteria
Site ratings, materials, controls, FAT/SAT, performance, spares, training, warranty, service and documentation are included.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Procurement Lead
Owns sourcing, tendering, commercial closure, contractual obligations and supplier escalation.
Supporting roles
Mechanical and Cooling Lead; Water and Environmental Lead; Commissioning Manager
Evidence required
Issued tender package and compliance matrix
Gate or milestone blocked
Vendor selection
Risk if delayed
Vendors may offer equipment that meets generic but not project conditions.
CLW-033Evaluate vendor compliance and lifecycle supportProcurementEvaluationProcurement Lead
CriticalTo be assessed
Show details for CLW-033
Task
Evaluate vendor compliance and lifecycle support
Completion criteria
Technical deviations, performance curves, materials, control interfaces, references, lead time, local service and lifecycle cost are assessed.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Procurement Lead
Owns sourcing, tendering, commercial closure, contractual obligations and supplier escalation.
Supporting roles
Mechanical and Cooling Lead; Operations Manager; Finance and Commercial Lead
Evidence required
Approved technical-commercial evaluation
Gate or milestone blocked
Contract award
Risk if delayed
Low bid may have weak local support or hidden derating.
CLW-034Award with performance, testing and support obligationsProcurementContractingProcurement Lead
CriticalTo be assessed
Show details for CLW-034
Task
Award with performance, testing and support obligations
Completion criteria
Contracts include guaranteed conditions, FAT/SAT, load tests, commissioning attendance, training, spares, warranty, AMC and remedies.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Procurement Lead
Owns sourcing, tendering, commercial closure, contractual obligations and supplier escalation.
Supporting roles
Legal Counsel; Commissioning Manager; Finance and Commercial Lead
Evidence required
Executed contracts and responsibility matrix
Gate or milestone blocked
Manufacturing
Risk if delayed
Performance gaps may lack contractual remedy.
CLW-035Approve and witness critical equipment FATFactory TestingFATCommissioning Manager
HighTo be assessed
Show details for CLW-035
Task
Approve and witness critical equipment FAT
Completion criteria
Approved procedures test controls, safeties, performance-relevant functions and interfaces; deviations are closed or transferred.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Commissioning Manager
Owns commissioning strategy, test plans, witnesses, execution, defects, retests and evidence.
Supporting roles
Mechanical and Cooling Lead; Quality Manager; OEM or System Vendor
Evidence required
Signed FAT reports and defect closure
Gate or milestone blocked
Shipment release
Risk if delayed
Defects may reach site and consume commissioning contingency.
CLW-036Inspect cooling and water installationConstructionInstallationQuality Manager
CriticalTo be assessed
Show details for CLW-036
Task
Inspect cooling and water installation
Completion criteria
Equipment, supports, pipework, slopes, valves, insulation, drains, sensors, labels, access, cleanliness and corrosion protection comply.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Quality Manager
Owns inspection plans, quality records, non-conformance, snag closure and evidence quality.
Supporting roles
Construction Manager; Mechanical and Cooling Lead; Water and Environmental Lead
Evidence required
Installation inspection records
Gate or milestone blocked
Pressure test and flushing
Risk if delayed
Installation defects can cause leaks, contamination or low flow.
CLW-037Complete pressure tests, flushing and cleaningConstructionTestingMechanical and Cooling Lead
CriticalTo be assessed
Show details for CLW-037
Task
Complete pressure tests, flushing and cleaning
Completion criteria
Systems pass approved pressure/leak tests and cleanliness criteria; flushing records and water disposal evidence are complete.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Mechanical and Cooling Lead
Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria.
Supporting roles
Quality Manager; Commissioning Manager; Water and Environmental Lead
Evidence required
Pressure, flushing and cleanliness reports
Gate or milestone blocked
Wet commissioning
Risk if delayed
Debris or leakage can damage equipment.
CLW-038Commission treatment and establish baseline chemistryConstructionWater TreatmentWater and Environmental Lead
CriticalTo be assessed
Show details for CLW-038
Task
Commission treatment and establish baseline chemistry
Completion criteria
Treatment equipment operates, dosing is controlled, water meets limits and sampling/response procedure is active.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Water and Environmental Lead
Owns water balance, source legality, quality, treatment, discharge and environmental obligations.
Supporting roles
Mechanical and Cooling Lead; OEM or System Vendor; Operations Manager
Evidence required
Commissioning results and baseline laboratory report
Gate or milestone blocked
Cooling functional testing
Risk if delayed
Untreated water can immediately foul or corrode systems.
CLW-039Test pumps, valves and hydraulic performanceCommissioningFunctionalMechanical and Cooling Lead
CriticalTo be assessed
Show details for CLW-039
Task
Test pumps, valves and hydraulic performance
Completion criteria
Duty/standby, flows, pressures, balancing, isolation, lead-lag, alarms and operating points meet design.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Mechanical and Cooling Lead
Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria.
Supporting roles
Commissioning Manager; Controls and Monitoring Lead; OEM or System Vendor
Evidence required
Signed hydraulic functional and balancing report
Gate or milestone blocked
Cooling system acceptance
Risk if delayed
System may not deliver required flow or redundancy.
CLW-040Test primary and terminal cooling equipmentCommissioningFunctionalCommissioning Manager
CriticalTo be assessed
Show details for CLW-040
Task
Test primary and terminal cooling equipment
Completion criteria
Capacity-relevant operation, safeties, turndown, controls, alarms, restart, airflow and room response pass.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Commissioning Manager
Owns commissioning strategy, test plans, witnesses, execution, defects, retests and evidence.
Supporting roles
Mechanical and Cooling Lead; OEM or System Vendor; Operations Manager
Evidence required
Signed equipment functional test reports
Gate or milestone blocked
Thermal load test
Risk if delayed
Equipment may not achieve site performance.
CLW-041Test sequences, failover and post-power recoveryCommissioningControlsControls and Monitoring Lead
CriticalTo be assessed
Show details for CLW-041
Task
Test sequences, failover and post-power recovery
Completion criteria
Lead-lag, staging, component failure, controller/sensor failure, power interruption and restoration follow approved sequence.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Controls and Monitoring Lead
Owns BMS/DCIM/EPMS points, sequences, alarms, integrations, access and reporting.
Supporting roles
Commissioning Manager; Mechanical and Cooling Lead; Operations Manager
Evidence required
Signed sequence and failover test report
Gate or milestone blocked
Integrated cooling test
Risk if delayed
Control logic may defeat physical redundancy.
CLW-042Test water storage, make-up, low-water and backup supplyCommissioningWater ResilienceWater and Environmental Lead
CriticalTo be assessed
Show details for CLW-042
Task
Test water storage, make-up, low-water and backup supply
Completion criteria
Levels, replenishment, source changeover, low-water alarms, emergency connections and response meet required autonomy.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Water and Environmental Lead
Owns water balance, source legality, quality, treatment, discharge and environmental obligations.
Supporting roles
Commissioning Manager; Operations Manager; Security Lead
Evidence required
Signed water resilience test report
Gate or milestone blocked
Cooling resilience acceptance
Risk if delayed
Cooling may stop during source interruption.
CLW-043Test leak detection, containment, isolation and escalationCommissioningLeak DetectionCommissioning Manager
CriticalTo be assessed
Show details for CLW-043
Task
Test leak detection, containment, isolation and escalation
Completion criteria
Representative leaks trigger correct zone, alarm, notification, shutoff/response and safe recovery without unintended impact.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Commissioning Manager
Owns commissioning strategy, test plans, witnesses, execution, defects, retests and evidence.
Supporting roles
Controls and Monitoring Lead; Operations Manager; HSE Manager
Evidence required
Signed leak scenario test report
Gate or milestone blocked
Environmental and operations acceptance
Risk if delayed
Leak controls may fail when IT equipment is exposed.
CLW-044Execute staged thermal load testCommissioningThermal LoadCommissioning Authority
CriticalTo be assessed
Show details for CLW-044
Task
Execute staged thermal load test
Completion criteria
Approved load, density, duration and ambient conditions produce acceptable rack inlet temperatures, humidity, flow, pressure and stability.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Commissioning Authority
Independently challenges test scope, witnesses critical tests and validates readiness and results.
Supporting roles
Commissioning Manager; Mechanical and Cooling Lead; Operations Manager
Evidence required
Thermal load report and trend data
Gate or milestone blocked
Cooling acceptance
Risk if delayed
Cooling performance under realistic IT load remains unproven.
CLW-045Test component loss and high-temperature responseCommissioningFailure ScenariosCommissioning Manager
CriticalTo be assessed
Show details for CLW-045
Task
Test component loss and high-temperature response
Completion criteria
Specified unit, pump, control or source failures maintain conditions within design or trigger timely controlled response and recovery.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Commissioning Manager
Owns commissioning strategy, test plans, witnesses, execution, defects, retests and evidence.
Supporting roles
Mechanical and Cooling Lead; Controls and Monitoring Lead; Operations Manager
Evidence required
Signed cooling failure-scenario reports
Gate or milestone blocked
Cooling resilience acceptance
Risk if delayed
Installed N+1 may not work in practice.
CLW-046Validate energy and water metering and KPI calculationsCommissioningEfficiencyControls and Monitoring Lead
HighTo be assessed
Show details for CLW-046
Task
Validate energy and water metering and KPI calculations
Completion criteria
Meters are accurate, boundaries match definitions and PUE/WUE-related cooling inputs can be calculated from retained data.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Controls and Monitoring Lead
Owns BMS/DCIM/EPMS points, sequences, alarms, integrations, access and reporting.
Supporting roles
Mechanical and Cooling Lead; Water and Environmental Lead; Operations Manager
Evidence required
Meter validation and KPI calculation report
Gate or milestone blocked
Sustainability reporting
Risk if delayed
Efficiency claims may be wrong or impossible to improve.
CLW-047Close cooling and water defects with retest evidenceCommissioningDefectsQuality Manager
CriticalTo be assessed
Show details for CLW-047
Task
Close cooling and water defects with retest evidence
Completion criteria
All critical defects close; corrections are retested; affected interfaces regress; remaining risk has authorised acceptance.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Quality Manager
Owns inspection plans, quality records, non-conformance, snag closure and evidence quality.
Supporting roles
Commissioning Manager; Mechanical and Cooling Lead; Operations Manager
Evidence required
Final defect register and signed retest evidence
Gate or milestone blocked
Cooling acceptance
Risk if delayed
Known defects may become operational failures.
CLW-048Approve cooling and water commissioning acceptanceCommissioningStage GateProject Director
CriticalTo be assessed
Show details for CLW-048
Task
Approve cooling and water commissioning acceptance
Completion criteria
Functional, resilience, thermal, leak, water and monitoring tests pass; evidence and residual-risk acceptance are complete.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Project Director
Owns end-to-end delivery, cross-workstream decisions, executive escalation and stage-gate readiness.
Supporting roles
Commissioning Authority; Operations Manager; Water and Environmental Lead
Evidence required
Signed cooling and water acceptance certificate
Gate or milestone blocked
Operations handover
Risk if delayed
Critical environmental systems may be handed over unproven.
CLW-049Approve cooling and water SOPs, MOPs and EOPsOperations ReadinessProceduresOperations Manager
CriticalTo be assessed
Show details for CLW-049
Task
Approve cooling and water SOPs, MOPs and EOPs
Completion criteria
Routine operation, chemistry, isolation, maintenance, high temperature, component failure, water shortage and leak procedures are validated.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Operations Manager
Owns operational acceptance, staffing, procedures, monitoring, maintenance and post-handover accountability.
Supporting roles
Facilities Manager; Water and Environmental Lead; HSE Manager; Document Controller
Evidence required
Approved and field-validated procedure set
Gate or milestone blocked
Operational acceptance
Risk if delayed
Staff may improvise during fast-moving environmental events.
CLW-050Activate maintenance, vendor support and sparesOperations ReadinessMaintenanceFacilities Manager
CriticalTo be assessed
Show details for CLW-050
Task
Activate maintenance, vendor support and spares
Completion criteria
Preventive plan, statutory tasks, AMCs, emergency contacts, chemicals, consumables, tools and critical spares are available.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Facilities Manager
Owns daily critical-facility operation, maintenance readiness, spares, rounds and emergency response.
Supporting roles
Procurement Lead; OEM or System Vendor; Operations Manager
Evidence required
Maintenance calendar, contracts and physical inventory
Gate or milestone blocked
Operational acceptance
Risk if delayed
Small component or chemistry failure may extend outage.
CLW-051Train and assess cooling and water operatorsOperations ReadinessTrainingOperations Manager
CriticalTo be assessed
Show details for CLW-051
Task
Train and assess cooling and water operators
Completion criteria
Assigned personnel demonstrate normal rounds, chemistry checks, alarm response, isolation, leak response and escalation.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Operations Manager
Owns operational acceptance, staffing, procedures, monitoring, maintenance and post-handover accountability.
Supporting roles
HR and Training Lead; Mechanical and Cooling Lead; Water and Environmental Lead
Evidence required
Training and practical competency records
Gate or milestone blocked
Operational acceptance
Risk if delayed
Operators may not recognise deterioration or respond safely.
CLW-052Activate water, discharge and environmental compliance calendarOperations ReadinessComplianceCompliance Manager
CriticalTo be assessed
Show details for CLW-052
Task
Activate water, discharge and environmental compliance calendar
Completion criteria
Sampling, consumption, discharge, chemical, approval-condition and renewal obligations have dates, owners and evidence locations.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Compliance Manager
Owns compliance obligations, evidence retention, renewals, audits and controlled exceptions.
Supporting roles
Water and Environmental Lead; Operations Manager; Document Controller
Evidence required
Operational compliance calendar
Gate or milestone blocked
Operational go-live
Risk if delayed
Missed conditions may trigger penalties or supply restrictions.
CLW-053Baseline operating trends and alarm responseOperations ReadinessMonitoringOperations Manager
HighTo be assessed
Show details for CLW-053
Task
Baseline operating trends and alarm response
Completion criteria
Normal temperature, humidity, energy, water, chemistry, flow and pressure trends are captured; alarm escalation is tested.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Operations Manager
Owns operational acceptance, staffing, procedures, monitoring, maintenance and post-handover accountability.
Supporting roles
Controls and Monitoring Lead; Facilities Manager
Evidence required
Baseline trend pack and alarm test report
Gate or milestone blocked
Stabilisation
Risk if delayed
Operations may lack reference data for early fault detection.
CLW-054Run seasonal performance and capacity reviewStabilisationOptimisationOperations Manager
HighTo be assessed
Show details for CLW-054
Task
Run seasonal performance and capacity review
Completion criteria
Actual load, PUE/WUE inputs, water quality, alarms, redundancy use, maintenance and peak-condition performance are compared with design.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Operations Manager
Owns operational acceptance, staffing, procedures, monitoring, maintenance and post-handover accountability.
Supporting roles
Mechanical and Cooling Lead; Water and Environmental Lead; Finance and Commercial Lead
Evidence required
Seasonal performance report and action register
Gate or milestone blocked
Optimisation / next expansion phase
Risk if delayed
Design assumptions may remain uncorrected as load grows.
CLW-055Revalidate cooling and water plan before each expansion phaseStabilisationExpansionMechanical and Cooling Lead
CriticalTo be assessed
Show details for CLW-055
Task
Revalidate cooling and water plan before each expansion phase
Completion criteria
Actual performance, source availability, approvals, capacity headroom, density and lessons learned update the next-phase design.
Dependency explanation
Predecessor tasks provide the approved input, evidence or readiness required for this task.
Accountable role
Mechanical and Cooling Lead
Owns cooling/mechanical design, equipment selection, redundancy, performance and test criteria.
Supporting roles
Operations Manager; Water and Environmental Lead; Design Manager
Evidence required
Approved expansion readiness review
Gate or milestone blocked
Next capacity release
Risk if delayed
Later phases may repeat obsolete assumptions or exhaust site resources.
This checklist is a project-management framework, not legal, regulatory, engineering or certification advice. Exact requirements vary by location, authority, facility design, operating model and project objectives. Validate applicability with qualified local professionals and the relevant authorities. Completing the checklist does not guarantee approval, certification, uptime or regulatory compliance.